Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL NEW
Permit Number - T02CM04316
Review Name: COMMERCIAL NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/12/2002 | PETER MCLAUGHLIN | ZONING | REVIEW | Passed | |
| 11/05/2002 | JIM EGAN | FIRE | REVIEW | Approved | |
| 12/09/2002 | MHAEBER1 | WATER | REVIEW | Approved | |
| 12/09/2002 | ANY | FLOODPLAIN | REVIEW | Approved | |
| 12/11/2002 | MARTIN HAEBERLE | PLUMBING-COMMERCIAL | REVIEW | Denied | An expansion tank is required for the proposed hot water heater. Plans indicate one on the HW heater detail but not on the isometric. Please clarify. Reference section 608.3 UPC. |
| 12/11/2002 | MARTIN HAEBERLE | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide rated fire dampers at penetrations of fire barriers, (storage areas). |
| 12/11/2002 | MARTIN HAEBERLE | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Panic hardware is required on exits. Reference section 1003.3.1.9 IBC. Revise code analysis and door schedule. 2. Storage areas are required to have a one-hour fire barrier both vertically and horizontally. Reference section 302.1.1 IBC. Indicate on plans and provide proposed assemblies to be used. 3. A ¾ hour door assembly required for storage room doors. Revise door schedule. 4. Fire barrier penetrations are required to be protected. See recessed hair dryer, electrical panels and conduit, etc. 5. Additional plumbing fixtures are required per table 2902.1 IBC. Revise plans to reflect additional fixtures or provide information that existing facilities meet the fixture requirements within 500 feet travel distance. 6. Handrails at the entrance ramp are required to have edge protection per section 405.9 ANSI A117.1. 7. Structural masonry level 1 inspections are to be done by third party special inspector. Revise general structural notes. 8. Architectural brick veneer details differs from structural details. Please coordinate |
| 12/12/2002 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 12/12/2002 | BOB SUBA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | 1.circuit MP-20 has no load @ panel schedule? 2.What is circuit MP-33 being used for? 3.Indicate the location of circuit on the electrical plan. 4.Provide a grounding electrode schematic for the multi-purpose building indicating electrode system ,grounding electrode conductor size,bonding to building steel-water piping-gas piping.5.The panel schedules indicate panels listed on sheet E-5 are new? Please clarify. 6.Please re-calculate the panel schedules to accurately sumarize the load as it's been designed,and make sure all circuit designations are accurate. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 12/16/2002 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |