05/24/2002 | JIM EGAN | FIRE | REVIEW | Approv-Cond | Conditional approval for canopy only. CNG installation requires seperate permit and submittal. |
06/06/2002 | MATT FLICK | ENGINEERING | REVIEW | Approved | |
06/07/2002 | MATT FLICK | FLOODPLAIN | REVIEW | Passed | |
06/07/2002 | MATT FLICK | SANITATION | REVIEW | Approved | |
06/19/2002 | DAVID RIVERA | ZONING | REVIEW | Denied | COMMENTS: Please attach a response letter with the next submittal, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. CODE SECTION/ DEVELOPMENT STANDARD 1. Lot split approval required prior to site plan approval. Attached is a copy of the lot split approval process. Please contact me for additional information regarding the lot split process. D.S. 2-02.2.1.A.2 2. Note the project address on the site plan. D.S. 2-02.2.1.A.3 3. a) Per L.U.C. Sec. 3.2.6.5.A, the front street perimeter yard is 20 feet or one and one-half (1½) the height of the proposed wall, measured from the street property line. Based on the proposed canopy height of 18 feet, the minimum required setback is 27 feet. Revise as required. b) Elevation drawings for canopy were not provided with this submittal. Please provide the elevation drawings to verify post location and setback requirements. D.S. 2-02.2.1.A.6/ D.S. 2-02.2.1.A.7/ L.U.C. 3.2.6.5.A 4. a) Per L.U.C. Sec. 3.3.3.5, two (2) Class II bicycle parking spaces are required. b) Provide a fully dimensioned Class II bicycle parking space detail on the plan. Refer to D.S. 2-09 for design criteria. D.S. 2-02.2.1.A.9/ L.U.C. 3.3.4/ L.U.C. 3.3.3.5/ D.S. 2-09 5. If applicable, provide a detail of proposed freestanding signage and outdoor lighting on the site plan. D.S. 2-02.2.1.A.13/ D.S. 2-02.2.1.A.25 |
06/19/2002 | JOE LINVILLE | NPPO | REVIEW | Denied | Submit native plant preservation plan or application for exception. LUC 3.8 |
06/19/2002 | JOE LINVILLE | LANDSCAPE | REVIEW | Denied | A landscape plan per DS 2-07 is required. Resubmitted plans will not be accepted without the required landscape plan and native plant preservation plan. The provisions of LUC 3.7 apply to the project. Provide a landscape plan including 10' street landscape border and screening per LUC Table 3.7.2-I. Additional comments may apply pending review of the requested landscape plans. |
06/24/2002 | PHIL SEADER | HANDICAP-SITE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/25/2002 | TAMI ACHONG | OUT TO CUSTOMER | Completed |