Review Date Reviewer's Name Type of Review Description Status Comments
01/29/2003 JIM EGAN FIRE REVIEW Approved
01/31/2003 PETER MCLAUGHLIN ZONING REVIEW Denied Site plan must be approved before bldg plan approval. See site review comments dated jan 31, 2003.
02/10/2003 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide information showing that the submitted MEC calculations conform to the International Energy Conservation Code (1998).
2. Provide detail showing that the appliance closets in the 2- and 3-bedroom units comply with Sections 602.1 and 602.2.1, IMC (2000).
02/10/2003 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Show routing and termination of condensate drains. Reference Sections 307.2.1 and 307.2.2, IMC (2000).
2. Show inverts and slope of building sewer line on drawing C1.1.
3. Recalculate plumbing schedule (shown on P1.2 and P1.3) using the values shown on Tables 7-3 and A-2, UPC.
4. Confirm the manufacturer's data and the minimum static pressure for P-3 is correct.
5. Recalculate pressure loss calculations and resize pipe in accordance with Sections 610.5 and 610.6, UPC.
6. Show how routing of drainage piping in Units 2, 4, 6, 7, and 9 conforms to Section 706.3, UPC.
7. Show routing and termination of T&P relief piping. Reference Section 608.5, UPC.
8. Resize drainage piping to conform to Table 7-5, UPC.
9. Clarify the waste and vent riser diagram. Are the vents to be combined or run separately through the roof?
10. Provide detail of water heater piping showing conformance to Section 608.3, UPC.
11. Provide reduced pressure backflow preventer assembly for site water supply.
02/25/2003 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Approved
03/04/2003 RAUL PALMA BUILDING-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
03/06/2003 MONICA VALDEZ OUT TO CUSTOMER Completed