Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T02CM00555
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/15/2002 | RAUL PALMA | BUILDING-COMMERCIAL | REVIEW | Approv-Cond | |
04/18/2002 | HOLLY PEARCE | PLUMBING-COMMERCIAL | REVIEW | Denied | Plumbing 1. Waste line Ismetric drawing does not comply with Sec 909 UPC 1994 Az. Code and the manufactures installation instructions. 2. Provide a water demand calculation on the plan. |
04/18/2002 | HOLLY PEARCE | MECHANICAL-COMMERCIAL | REVIEW | Passed | |
04/18/2002 | PATRICIA GEHLEN | ZONING | REVIEW | Denied | |
04/23/2002 | RANDY SCHULER | ELECTRICAL-COMMERCIAL | REVIEW | Denied | SECOND REVIEW E-1 SERVICE SEE RED LINE SET FOR ADDITIONAL INFORMATION 1) OK 2) OK 3) OK 4) Provide TEP AFC to POA . The downstream panel boards must be listed/labeled series rated for the highest fault at their line terminals. This must be noted along with the line terminal fault current on the plan. NEW: Let through values may not be used. Please see red line set for additional commentary. 5) OK 6) Provide the line side conductor sizes for the service disconnects. Note: If an equipment bonding conductor on the line side of the disconnect is installed you must use 99NEC 250-66 for appropriate sizing. See 99NEC 250-102(c). NEW: The 600kcmil service entrance conductor requires a minimum 1/0 copper equipment bonding jumper. See red line set, and comment above for additional information. E-3 1) The piping serving the 'C' fixtures must be a minimum of 5' from the inside wall of the pool. 99NEC 680-10 NEW: Comment not addressed. See redline set for clarification. 2) OK 3) OK 4) Indicate by note the #2 copper bond be routed back to the pool equipment and pool cover motor per 99NEC 680-22(a)(4). NEW: See red line set for clarification. 5) OK NEW COMMENTS April 23, 2002 1) PG E-3 It appears the restrooms and pool equipment should circuit to panel PP not PH as shown. 2) PG E-1 Provide the loads individually in PP panel schedule. |
05/01/2002 | DOUG WILLIAMS | FLOODPLAIN | REVIEW | Denied | Provide approved Development Plan with submittal - the approved Development Plan may be walked through for Site approval. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
05/03/2002 | MONICA VALDEZ | OUT TO CUSTOMER | Completed |