Permit Number: T02BU02964
Parcel: Unknown

Address:
3630 E FELIX BL

Review Status: Completed

Review Details: GRADING

Permit Number - T02BU02964
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/06/2003 ELIZABETH EBERBACH ENGINEERING REVIEW Denied SUBJECT: Drexel Manor Grading Plan Engineering Review
REVIEWER: Elizabeth Eberbach
ACTIVITY NUMBER: T02BU02964

SUMMARY: The "PRELIMINARY - NOT FOR CONSTRUCTION" Grading Plan and a potion of the geotechnical report was received by Engineering on November 25, 2002. GRC percolation results were received on January 29, 2003. The Tentative Plat has not been approved. Engineering has reviewed the received items and does not recommend approval of the Grading Plan at this time.

GRADING PLAN COMMENTS
1) City of Tucson Development Standards (DS) Section No.2-03.5.2: The grading plan cannot be approved unless it is in conformance with an approved tentative plat. Provide revisions to the Grading Plan per the revised / current Tentative Plat comments. Weir data, scupper data, basin elevations, flows, and other drainage details on the Grading Plan shall match the Tentative Plat and drainage report.
2) DS Sec.2-03.2.4.L.5: Submit documentation from Pima County for acceptance of proposed construction in Pima County right-of-way, and, that Pima County accepts maintenance responsibility for the swales along Drexel Road and Benson Highway to prevent flows from entering the project's basins or channels.
3) Boundary distances and bearings shall match boundary closure calculations and approved Final Plat.
4) Indicate datum location on a plan view and tie project to basis of bearing and shown section bearings;
5) Clarify flows entering basins per approved Tentative Plat. Provide velocity, Q100, depth of flow, for each v-channel, rectangular channel, and 18" CMP detail.
6) Identify existing slabs and other existing structures. On plan view, label description of removal or relocation.
7) On sheet 1, add Tentative Plat general notes 8 and 11 and Residential Cluster note 5 to the Grading Plan notes.
8) On sheets 2 and 4, dimension cul-de-sac radii.
9) On sheets 2, 3, & 4, clarify the two delineations of grading limits. Grading limits, shown on index map, shall match grading limits shown on sheets 2, 3, & 4.
10) The PC COT jurisdictional limits overlap grading limits on sheet 4. Clarify linetype.
11) On sheet 4, label existing public right-of-way dimensions (and any MS&R future right-of-ways) and recordation data for Drexel Road. Show Pima County right-of-way dimension.
12) On sheet 6, detail 4, dimension rip rap area for proposed outlet at basin DET4.
13) Correct weir label ("WR-1"?) for detail 6 on sheet 7. Provide construction detail showing how flow is directed to catch basin for this detail. Provide slope grades, flow arrows and/or other indicators for grading.
14) Where is boring location map? Provide a complete copy of Geotechnical report. A portion of the report appears to be missing.
15) Add note to Grading Plan regarding typical slope treatments per page 10 and 11 of geotechnical report.
16) IBC Chap 36 Sec 11: A grading bond shall be posted in the amount of $41,500 for native seeding. If grading construction does not commence within 60 days after grubbing, the disturbed area shall be native seeded within 30 days following the expiration of the 60 day period.

Further grading comments may be forthcoming upon resubmittal due to outstanding issues with Tentative Plat. Address all comments for Tentative Plat prior to resubmittal. Submit soils report with addendum, revised Drainage Report, and a copy of the approved Tentative Plat. The next submittal should address all the above items and any current comments for Tentative Plat. If you have questions or want to set up a meeting, call me at 791-5550, extension 2204.

Elizabeth Eberbach, PE
Civil Engineer
Engineering Section
Development Services
02/06/2003 ELIZABETH EBERBACH FLOODPLAIN REVIEW Passed
02/10/2003 PATRICIA GEHLEN ZONING REVIEW Denied Zoning
2/10/2003
Grading plans may not be reviewed and approved until a copy of the approved tentative plat is included in the submittal package and Engineering has approved the plans
02/11/2003 PATRICIA GILBERT NPPO REVIEW Denied An approved tentative plat is required prior to grading plan approval.

Submit the approved Tentative plat, landscape and native plant preservation plan.

Pre-permit inspection is required. Once Engineering has approved the grading plan please call to schedule a pre-permit inspection. 791-5640 ext. 1140.
02/14/2003 LOREN MAKUS NPDES REVIEW Denied The Stormwater Pollution Plan is not approved.
1. Provide signed owner/project manager certification.
2. Clearly show all discharge locations on the plan.
Revise the plan and submit three copies of the plan and accompanying report.

Final Status

Task End Date Reviewer's Name Type of Review Description
05/19/2003 TAMI ACHONG OUT TO CUSTOMER Completed