Review Date Reviewer's Name Type of Review Description Status Comments
07/29/2002 MATT FLICK ENGINEERING REVIEW Denied ENGINEERING REVIEW COMMENTS:

1. Barriers are necessary around most of the retention areas.

2. Submit approvals for offsite construction on private property.

3. Any construction in public rights-of-way will require a right -of-way use permit from the Department of Transportation (791-5100).

4. Parcel is subject to HDZ. Indicate how slope stabilization complies with Dev. Std. 9-04.3.3.

5. Cut/fill slopes are to be a minimum of two feet (2') from property boundaries.

6. Use non-COT title block.

7. Add reference to Chapter 36 of the IBC (2000) on the ttile sheet in addition to Chapter 33 of the UBC.

8. The Development Standard (Detention/Retention Manual) requires spillways capable of discharging the undetenained 100-year discharge, with no damage, for beasins formed by berms.

9. Check grading where basins are higher than surrounding ground or much lower than surrounding ground.

10. Indicate how water is to be conveyed to catch basin at Firehole River Way/Campana Drive.
07/29/2002 MATT FLICK NPDES REVIEW Approved NPDES COMMENTS:

SWPPP will have to be resubmitted for approval if changes to the grading plan revise the grading or drainage patterns.
07/29/2002 MATT FLICK FLOODPLAIN REVIEW Denied FLOODPLAIN COMMENTS:

1. A Floodplain Use Permit is necessary ($50 application fee, $200 if an engineering study is submitted) prior to grading plan approval.

2. Most of the retention basin require barriers.

3. If basins are formed by a berm, Section 3.3.4 - Emergency Spillways of the Detention/Retention Manual requires emergency spilweays to pass the undetained 100-year flow. See the Detention/Retention Manual for more information.
07/31/2002 PATRICIA GILBERT NPPO REVIEW Denied Native Plant Preservation Pre-permit inspection is required. To schedule call 791-5640, ext. 1140.
07/31/2002 MICHAEL ST. PAUL ZONING REVIEW Denied See Engineering, Floodplain and NPPO comments.

Final Status

Task End Date Reviewer's Name Type of Review Description
08/01/2002 LISA LESNY OUT TO CUSTOMER Completed