Permit Review Detail
Review Status: Completed
Review Details: GRADING
Permit Number - T02BU00582
Review Name: GRADING
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/21/2002 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | SUBJECT: Tag Elementary School, Grading plan T02BU00582 (First Review) T14S, R15E, Section 2 RESUBMITTAL REQUIRED: Grading Plan and Drainage Report The Grading Plan and Drainage Report cannot be approved as submitted. Please address the following review comments prior to the next submittal. Grading plan: 1. The grading differential for this project exceeds the 2.0-foot allowed in Section 13 of the 2000 IBC. Please revise per code. 2. Letter or number the outlet detail on sheet. 2 and call out that detail, where applicable, on sheet. 1. 3. List the amounts of cut and fill. Not the difference between the two. 4. Please call out all grade breaks in the P.A.A.L. Drainage report: 1. The U.S. Geological quadrangle maps (Figure 4) are generally not accepted per S.M.D.D.F.M. Chapter 2.3.1.3.A. Please explain. 2. Show the project boundary on figure 4 per S.M.D.D.F.M. Chapter 2.3.1.3.A.3. 3. Page 8 states that there is a copy of the project attached to the report, please attach a copy. If you have any questions, I can be reached at 791-5550 or pmachad2@ci.tucson.az.us Paul Machado Senior Engineering Associate |
| 03/21/2002 | PAUL MACHADO | FLOODPLAIN | REVIEW | Denied | |
| 03/22/2002 | LOREN MAKUS | NPDES | REVIEW | Denied | No Stormwater (NPDES) review is required. Disturbed area is less than 5 acres. |
| 03/22/2002 | JOE LINVILLE | NPPO | REVIEW | Denied | Approved copy of the native plant preservation required prior to plan approval. NPPO pre-permit inspection required prior to plan approval. Call 791-5550 Ext. 118 to schedule |
| 03/25/2002 | PATRICIA GEHLEN | ZONING | REVIEW | Denied | Zoning 3/25/2002 Zoning will not review grading plans until Engineering/Floodplain has approved. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 05/15/2002 | MONICA VALDEZ | OUT TO CUSTOMER | Completed |