Permit Review Detail
Review Status: Completed
Review Details: OTHER
Permit Number - T01CM03303
Review Name: OTHER
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/03/2001 | JAMES TATE | FLOODPLAIN | REVIEW | Approved | |
| 08/06/2001 | HOLLY PEARCE | PLUMBING-COMMERCIAL | REVIEW | Denied | Plumbing 1. Civil site plan indicates a 3" building sewer, plumbing plans indicate a 4" being reduced to 3", this does not comply with Sec 311.5 UPC 1994 Az. Code. Civil site plan also indicates that a backwater valve will be required on the sewer, indicate where on the plan and provide a detail of the access required on the plan. 2. T&P Shall discharge to the exterior of the building. NOTE: The drinking fountain detail on L5 shall be approved by Pima County Dept. of Environmental Quality--- Eric Shepp 740-3959. |
| 08/07/2001 | DAN CASTRO | ZONING | REVIEW | Approved | |
| 08/08/2001 | RANDY SCHULER | ELECTRICAL-COMMERCIAL | REVIEW | Denied | E-1 1) The fixture schedule indicates a 100-watt HPS fixture for the basketball ball courts however the submittal indicates a 1000-watt HPS. 2) The entire pole and pole foundation detail does not match the design depicted on page S1, the soils report, or the structural calculations. E-3 1) It appears the circuitry in the comfort station should be circuited to panel A1 not P1 as shown. E-4 1) The loads for the basketball lights in the panel appear to be incorrect. Based on a 1000-watt fixture the VA load is approximately 1150 VA per fixture. 2) Provide a fault current analysis and equipment withstand ratings. 99NEC 110-3, 110-9, 110-10. 3) Provide a minimum #4 copper grounding electrode conductor for panel A. 99NEC 250-66 4) Remove the #6 ground in the service lateral. Replace with a minimum #4 cu neutral conductor. 99NEC 250-24(b) 5) Connect the grounding electrode conductor to the neutral and main bonding jumper in panel A. 99NEC 250-28, 250-30(a)(2) 6) Locate the basketball lighting controller contactors on the plan. 7) Provide a grounding electrode system at panel A1. 99NEC 250-32, 250-66 |
| 08/13/2001 | PHIL SEADER | BUILDING-COMMERCIAL | REVIEW | Denied | |
| 08/15/2001 | TOM CLARK | WATER | REVIEW | Approved | |
| 08/15/2001 | PHIL SEADER | BUILDING-COMMERCIAL | RECEIVED | Completed | |
| 09/05/2001 | GERRY KOZIOL | WWM | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/25/2001 | JKOZUCH | OUT TO CUSTOMER | Completed |