Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T01CM00360
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/23/2001 | DAVID RIVERA | ZONING | REVIEW | Approved | |
01/23/2001 | DOUG WILLIAMS | FLOODPLAIN | REVIEW | Approved | |
01/24/2001 | JIM EGAN | FIRE | REVIEW | Approved | |
01/25/2001 | PHIL SEADER | BUILDING-COMMERCIAL | REVIEW | Approved | |
02/01/2001 | RANDY SCHULER | ELECTRICAL-COMMERCIAL | REVIEW | Denied | |
02/05/2001 | HOLLY PEARCE | PLUMBING-COMMERCIAL | REVIEW | Denied | See comments under Mechanical. |
02/05/2001 | HOLLY PEARCE | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide the manufactures name, listing, design pressure, type and schedule and installation standards for the CNG lines. Put on the plans. 2. Move the Purge Air Line from the side of the Island ( Sec B P2.2 to the North side of the column. Physical damage could happen with it exposed on the side of the island. Provide calculations showing Expansibility in the 4 inch PVC pipe. Provide an expanable joint at the dispenser. 4. Vent the 4 incn PVC pipe at the compressor area with a Tee and a 90 degree elbow, with a insect screen. TAKE NOTE: Pressure Safety Valve ( Relief Valve) shall comply with A.S.M.E. Rules. Shut-OFF valve ( Supplied w/tank) ( Isolation Valve) Shall be ALARMED. |
02/07/2001 | TGRIFFUS | WWM | REVIEW | Passed |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
02/12/2001 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
02/12/2001 | DELMA ROBEY | APPROVAL SHELF | Completed |
02/07/2001 | DELMA ROBEY | REJECT SHELF | Completed |