Plan Review Detail
Review Status: Completed
Review Details: MINOR SUBDIVISION REVIEW
Plan Number - S20-076
Review Name: MINOR SUBDIVISION REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/07/2021 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 04/07/2021 | SBEASLE1 | UTILITIES | SOUTHWEST GAS | Passed | |
| 04/07/2021 | SBEASLE1 | PIMA COUNTY | WASTEWATER | Reqs Change | To Applicant: Please contact Pima County Wastewater at email: Sewer@Pima.gov or phone (520) 724-6500 to request their approval for wastewater. Submit their approval document to the City of Tucson with your next submittal. |
| 04/07/2021 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Reqs Change | To Applicant: Please contact Tucson Water. Request a Water Availability letter. Include the Letter in your next submittal for this permit. Mayor and Council cannot grant final approval until water is assured and available |
| 04/07/2021 | SBEASLE1 | OTHER AGENCIES | U. S. POST OFFICE | Passed | |
| 04/07/2021 | SBEASLE1 | OTHER AGENCIES | PIMA ASSN OF GOVTS | Passed | |
| 04/08/2021 | SBEASLE1 | UTILITIES | TUCSON ELECTRIC POWER | Approved | 04/07/21 Tucson Electric Power Co. (TEP) has reviewed and has no objection the Minor Subdivision review - 1137 E. Bilby Road, submitted April 7, 2021. Please call the New Construction Department at 520-918-8300 to apply for service. Submit a final set of approved plans including electrical load and offsite improvement plans to determine how TEP will serve this development. If easements are required, they will be obtained by separate instrument. Removal or relocation of existing TEP facilities will be at the Developer’s expense. Thank you kindly, Diane Geerligs, Right of Way Agent Tucson Electric Power Company 3950 E. Irvington Rd. | Tucson, AZ 85714-2114 Mail Stop Land Resources RC131 (o) 520-396-2536| (m) 520-730-1974 | (f) 520-545-1419 dgeerligs@tep.com |
| 04/08/2021 | ED ABRIGO | PIMA COUNTY | ASSESSOR | Passed | 04/08/21 Passed by Julieann Arechederra. Assessor's Office email: Julieann.Arechederra@pima.gov |
| 04/27/2021 | ROBERT SHERRY | PLUMBING-RESIDENTIAL | REVIEW | Completed | |
| 05/03/2021 | SSHIELD1 | LANDSCAPE | REVIEW | Passed | |
| 05/03/2021 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | FROM: Development Services Department Zoning Review PROJECT: 1137 E Bilby Rd FINAL PLAT (1st Review) S20-076 TRANSMITTAL DATE: May 3, 2021 DUE DATE: May 5, 2021 2-07.1.0 APPLICABILITY Final plats, block plats, minor subdivisions, and condominium plats shall be prepared according to the requirements provided below. Hereafter referred to as “plat” or “plats.” A final plat serves as a survey document suitable for recordation of all or part of an approved tentative plat, if applicable. The final plat must conform to the approved tentative plat or site plan in lot configuration, design, and required conditions of development. The final plat, once approved, is recorded in the Pima County Recorder’s Office. The final plat is kept on file and becomes part of the permanent record for the subject site. 1. Provide a final plat document that meets the requirements of Administrative Manual 2-07. 2. A separate residential plot plan will be required to be submitted for reference only. This plan must meet the requirements of a residential plot plan found at: https://www.tucsonaz.gov/files/pdsd/forms/Residential_Plot_Plan_Requirements.pdf. If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov |
| 05/03/2021 | SBEASLE1 | COT NON-DSD | PARKS & RECREATION | Approved | Email from: Howard Dutt To: CDRC Mon 5/3/2021 11:04 AM No existing or proposed Tucson Parks and Recreation facilities are affected by this Minor Subdivision. Howard B. Dutt, RLA, Landscape Architect Tucson Parks and Recreation (520) 837-8040 |
| 05/04/2021 | JOSE ORTIZ | COT NON-DSD | TRAFFIC | Approved | Email from: David Stiffey To: CDRC Tue 5/4/2021 3:29 PM Approved. David Stiffey, Program Coordinator City of Tucson Transportation and Mobility |
| 05/05/2021 | KAY MARKS | PIMA COUNTY | ADDRESSING | Reqs Change | (The ATTACHED PDF mentioned below can be viewed online: www.TucsonAz.gov/Pro. See the Documents section.) Email from: Robin Freiman <Addressing@pima.gov> To: CDRC Wed 5/5/2021 11:33 AM Minor Subdivision review - 1137 E. Bilby Road, S20-076, 1st submittal is being Returned for Corrections by Pima County Addressing. The attached pdf contains Addressing’s comments. Please let me know if you have any questions. Thank you, Robin Freiman, Addressing Official Pima County Development Services Department 201 N Stone AV – 1st Floor Tucson, AZ 85701, (520) 724-7570 |
| 05/21/2021 | SBEASLE1 | ENGINEERING | REVIEW | Needs Review | |
| 05/21/2021 | JIM EGAN | COT NON-DSD | FIRE | Needs Review | |
| 05/21/2021 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Passed |