Plan Review Detail
Review Status: Completed
Review Details: FINAL PLAT - REVIEW
Plan Number - S20-059
Review Name: FINAL PLAT - REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/15/2021 | LIZA CASTILLO | UTILITIES | TUCSON ELECTRIC POWER | Approved | 01/15/21 Tucson Electric Power Co., (TEP) has reviewed and approves the final plat submitted on December 15, 2020. Electric service will be provided to this subdivision in accordance with the rules and regulations approved by the Arizona Corporation Commission. If there are any questions, please contact me at 520-401-9895. Thank you, Mary Burke, Senior Right of Way Agent Tucson Electric Power Co., Land Resources – RC 131 3950 E. Irvington Road Tucson, AZ 85714-2114 Cell - 520-401-9895, mburke@tep.com |
01/28/2021 | SAMUEL ROGERS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Samuel Rogers Planner PDSD Zoning Review Section PROJECT: Final Plat for Corbett Village FLD Subdivision Final Plat (1st Review) S20-059 TRANSMITTAL DATE: 01/28/2021 DUE DATE: 01/05/2021 COMMENTS: Please resubmit revised drawings along a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-07. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). The review comments include the actual standard first with the applicable Administrative Manual section number and the following paragraph is the actual comment related to the specific item that must be addressed. If you need to review the sections listed below click on the link or copy it in the address bar of your internet program. http://www.amlegal.com/nxt/gateway.dll/Arizona/tucson_az_udc/administrativemanual?f=templates$fn=default.htm$3.0$vid=amlegal:tucson_udc_az This link will take you directly to the section used for the standards review. The UDC & TSM requirements are in the Unified Development Code and can be viewed at the same web link as above SECTION 2-07.0.0: FINAL PLAT, BLOCK PLAT, MINOR SUBDIVISION, AND CONDOMINIUM PLAT APPLICATIONS Section 2-07.1.0 APPLICABILITY 2-07.2.0 APPLICATION SUBMITTAL REQUIREMENTS 2-07.3.0 SUBMITTAL TIMING 2-07.4.0 FORMAT REQUIREMENTS 2-07.5.0 CONTENT REQUIREMENTS 2-07.6.0 APPROVAL DOCUMENTS AND PROCEDURE 2-07.1.0 APPLICABILITY Final plats, block plats, minor subdivisions, and condominium plats shall be prepared according to the requirements provided below. Hereafter referred to as “plat” or “plats.” A final plat serves as a survey document suitable for recordation of all or part of an approved tentative plat, if applicable. The final plat must conform to the approved tentative plat or site plan in lot configuration, design, and required conditions of development. The final plat, once approved, is recorded in the Pima County Recorder’s Office. The final plat is kept on file and becomes part of the permanent record for the subject site. (Am. Admin. Directive, 5/14/2013) 2-07.2.0 APPLICATION SUBMITTAL REQUIREMENTS Plat application packets are available from the PDSD Department. Completed applications and accompanying materials are submitted to the PDSD. Incomplete or inaccurate applications will not be accepted, nor will any application in which the pre-application conference or neighborhood meeting requirements have not been met. Should an incomplete submittal be accepted for review, the applicant should be aware that, because of a lack of information, the review will take longer since comments cannot be finalized until after the resubmittal when the required information is provided. The types of documents and the specific number of copies required of each of the documents are on the PDSD website or may be obtained from the CDRC office. The following documents and information shall be submitted upon application: 2.1 Application Form A completed application signed by the property owner or authorized designee; 2.2 Plat A plat must be prepared to the format and content requirements described herein; and, 2.3 Fees Fees in accordance with Section 4-01.0.0, Development Review Fee Schedule. 2-07.3.0 SUBMITTAL TIMING Review of final plats is normally initiated after the tentative plat has been approved, unless concurrent tentative and final plat submittal has been approved by the PDSD prior to submittal. Final plats may also be submitted for review prior to the approval of a tentative if a minimum of one review of the tentative plat have occurred. In any case, submittal of the final plat prior to approval of the tentative plat is done at the applicant’s risk since changes could be required of the tentative that may affect the final plat. 2-07.4.0 FORMAT REQUIREMENTS Plats must: 4.1 Be on a 24-inch by 36-inch sheet(s) folded to the eight and one-half inch by 11-inch format shown in Exhibit I. The plat may comprise several sheets showing various elements of required data; 4.2 Be prepared on materials that can be transferred to double-matt Mylar reverse read; 4.3 Have a two-inch margin on the left side and one-half inch margins on the remaining sides to comply with standardization requirements of state law for recorded plats; 4.4 Be drawn to a scale of no more than one inch equals 40 feet; and, 4.5 All lettering and dimensions shall be three-thirty-seconds inch in height. 1. COMMENT: DP20-0077 must be issued prior to the approval of this Final Plat. 2-07.5.0 CONTENT REQUIREMENTS 5.1 General 2-07.5.1.E Provide a title block in the lower right corner of each sheet with the following information: 2-07.5.1.E.1 Subdivision name; number of blocks, lots, and/or units; and common area; 2. COMMENT: ADD “FLD” to Title Block 2-07.5.2 General Notes The plat must include the following general notes. Additional notes specific to each project are required when pertinent. Fill in the blanks with the project-specific information. 2-07.5.3 Standard Paragraphs The plat must include the following statements, as applicable. All signatures must be in permanent, black, India ink and be accompanied by a notary signature and seal. 2-07.5.3.E Assurances 3. . COMMENT: Add a signature line for the City of Tucson Planning and Development Services Department Director under the Assurance Block. The following ASSURANCE block must be placed on the plat’s first sheet. ASSURANCES “This is to certify that all improvements, such as streets, sidewalks, sewers, water and utility installation, drainage and flood control facilities, and monuments, required by the City of Tucson have been completed or the future completion of such improvements has been assured by a land trust financial assurance agreement, the posting of performance bonds, an escrow account, letter of credit, or other security as the City of Tucson deems necessary and proper. In the event that any such assurance expires, lapses or is otherwise inadequate to assure the completion of assurable infrastructure, the city may suspend the issuance of building permits or certificates of occupancy.” City of Tucson Planning and Development Services Department Director City of Tucson Engineer If you have any questions about this transmittal, Contact Samuel Rogers at Samuel.Rogers@tucsonaz.gov. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised final plat. |
02/05/2021 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | 1. Provide the correct signature lines for the assurances block. Provide a signature line for the Director of Planning and Development Services and a signature line for the City Engineer. |
02/08/2021 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | |
12/15/2020 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
12/15/2020 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Approved | See document: "2_Water Availability Ltr, 02.18.20, Tucson Water" |
12/15/2020 | SBEASLE1 | PIMA COUNTY | WASTEWATER | Approved | Sewer Layout Approval Issued Date: 10/30/2020 RECORD: P20WS00059 The WLB Group, Inc. Pepper Viner, 5633 E Grant Rd, Tucson, AZ 85712 Project: CORBETT VILLAGE The Pima County Development Services Department has reviewed the Final Plat for proposed sewer design for the above-referenced project and hereby approves the above referenced submittal of the Final Plat, based upon PCRWRD Engineering Design Standards (EDS) 2016. Please note any changes and/or revisions to the approved plans shall require a re-submittal to the department for review and evaluation. Pima County Development Services Department 201 N. STONE AVENUE, 1st FLOOR, TUCSON, ARIZONA 85701-1207 |