Plan Review Detail
Review Status: Completed
Review Details: FINAL PLAT - REVIEW
Plan Number - S20-027
Review Name: FINAL PLAT - REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/31/2020 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
08/31/2020 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Approved | May 4, 2020 Atwell 4700 E. Southern Ave. Mesa, AZ 85206 Attn: Dennis E. Roberts, P.E. SUBJECT: Water Availability for Project: 6700-6800 Block of E. Camino Boleadoras, APN: 141366800,880,890,900,910,920,930,940 & 960, Case #: WA3112, T-15 R-15 S-19, Lots: 9999, Location Code: TUC, Total Area: 106.97 ac, Zoning: PAD-7 WATER SUPPLY Tucson Water will provide water service to this project based on the subject zoning of the above parcels. Tucson Water has an assured water supply (AWS) designated from the State of Arizona Department of Water Resources (ADWR). An AWS designation means Tucson Water has met the criteria established by ADWR for demonstration of a 100-year water supply - it does not mean that water service is currently available to the subject project. WATER SERVICE The approval of water meter applications is subject to the current availability of water service at the time an application is received. The developer shall be required to submit a water master plan identifying, but not limited to: 1) Water Use; 2) Fire Flow Requirements; 3) Offsite/Onsite Water Facilities; 4) Loops and Proposed Connection Points to Existing Water System; and 5) Easements/Common Areas. Any specific area plan fees, protected main/facility fees and/or other needed facilities' cost, are to be paid by the developer. If the existing water system is not capable of meeting the requirements of the proposed development, the developer shall be financially responsible for modifying or enhancing the existing water system to meet those needs. This letter shall be null and void two years from the date of issuance. Issuance of this letter is not to be construed as agency approval of a water plan or as containing construction review comments relative to conflicts with existing water lines and the proposed development. If you have any questions, please call New Development at 791-4718. Michael Mourreale, P.E., Engineering Manager Tucson Water Department |
09/24/2020 | SBEASLE1 | PIMA COUNTY | WASTEWATER | Reqs Change | To Applicant: Please provide an approval document in the next submittal. The Applicant is responsible for obtaining review and approval for wastewater from Pima County (email: Sewer@Pima.gov) prior to Mayor & Council approval of this final plat. |
09/29/2020 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
09/30/2020 | SBEASLE1 | PIMA COUNTY | ADDRESSING | Reqs Change | (The ATTACHED PDF mentioned below can be viewed online: www.TucsonAz.gov/Pro. See the Documents section.) La Estancia parcel 4, S20-027 Final Plat, 2nd submittal, is being Returned for Corrections by Pima County Addressing. The attached pdf contains Addressing’s comments. Please let me know if you have any questions. Thank you, Robin Freiman, Addressing Official Pima County Development Services Dept (520) 724-7570 |
10/02/2020 | LIZA CASTILLO | UTILITIES | TUCSON ELECTRIC POWER | Approved | Tucson Electric Power Co., (TEP) has reviewed and approves the final plat for La Estancia Phase 2, Parcel 4. Electric service will be provided to this subdivision in accordance with the rules and regulations approved by the Arizona Corporation Commission. If there are any questions, please contact me at 520-401-9895 Thank you, Mary Burke, Senior Right of Way Agent Tucson Electric Power Co. Land Resources – RC 131 3950 E. Irvington Road Tucson, AZ 85714-2114 Cell - 520-401-9895 mburke@tep.com |
10/09/2020 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | S20-027 1) Previous Comment 4/5. These comments were not addressed. Provide a copy of any drainage easements or agreements showing required offsite drainage infrastructure that needs to be built to support this subdivision. Provide a copy of the required assurance agreement on next submittal. Required improvements to be described in the assurance agreement 2) Approval of the associated Tentative Plat is required prior to final plat approval John Van Winkle, P.E. John.VanWinkle@tucsonaz.gov |
10/14/2020 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | DATE: Oct. 14, 2020 RETURNED FOR CORRECTIONS NOTICE Your Next Steps: Resubmittal of your updated/corrected documents IMPORTANT: On the Filedrop page, select the box: "Site Review/CDRC..." when sending your next submittal. DESCRIPTION: FINAL PLAT - PARCEL 4, La Estancia de Tucson, Phase 2. PERMIT/ACTIVITY: S20-027 FEE BALANCE: $0 (zero) Thank you for the payment. SEE REVIEW COMMENTS and your submitted documents on PRO: www.tucsonaz.gov/pro (If information is not available, check back later after data transfers to PRO.) - Home page, Activity Search, enter the Activity/Permit Number - Permits - click on blue tab - Reviews - click on Review Details - Documents - click on View to the right of each document YOUR NEXT STEP: Submit documents to the Filedrop https://www.tucsonaz.gov/file-upload-pdsd 1) Comment Response Letter (your response to the reviewer's Requires Change comments) 2) Plan Set (all pages, full set, even if no changes were made) 3) Any other documents requested by review staff - Name the 3rd submittal documents starting with the submittal number, for example: 3_Plan_Set IMPORTANT: On the Filedrop page, select the box: "Site Review/CDRC..." when sending your next submittal. Thank you. Sharon Beasley, Permit Specialist City of Tucson Planning and Development Services email: COTDSDPermits@TucsonAz.gov |