Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: S19-088
Parcel: Unknown

Review Status: Completed

Review Details: LOT SPLIT REVIEW

Plan Number - S19-088
Review Name: LOT SPLIT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/11/2020 SBEASLE1 START PLANS SUBMITTED Completed
02/12/2020 DAVID RIVERA ZONING REVIEW Approv-Cond PDSD TRANSMITTAL
FROM: David Rivera - Zoning Review Section
PROJECT: 1115 E Blanton Dr.
S19-088
Land Split - R-2 Zoning
TRANSMITTAL DATE: February 12, 2020
The land split, has been reviewed by the Zoning Review Section for minimal compliance with the Administrative Manual Section 2-08. It has been determined that the submitted plans do not provide sufficient information to complete a plan review. The following items need to be addressed prior to re-submittal.
1. Zoning conditionally approves the Lot Split. Prior to recordation of the lot split the DDO application must be processed and approved. The DDO comments are provided on the next page.
PDSD TRANSMITTAL
FROM: David Rivera - Zoning Review Section
PROJECT: 1115 E Blanton Dr.
S19-088
Land Split - R-2 Zoning
TRANSMITTAL DATE: February 12, 2020
The land split, has been reviewed by the Zoning Review Section for minimal compliance with the Administrative Manual Section 2-08. It has been determined that the submitted plans do not provide sufficient information to complete a plan review. The following items need to be addressed prior to re-submittal.

1. Zoning conditionally approves the Lot Split. Prior to recordation of the lot split the DDO application must be processed and approved. The DDO comments are provided on the next page.

2. List the DDO case number next to right corner of the plot plan sheet. The next submittal of the Lot Split shall include the approved DDO documentation and stamped and signed sheets by Mark Castro.







PDSD TRANSMITTAL
FROM: David Rivera,
Zoning Review Section

PROJECT: S19-088 - Lot Split / R-2 Zoning (2 lots proposed)
ADDRESS: 1115 E. Blanton Drive
TRANSMITTAL: January 30, 2020
COMMENTS: the following comments are relative to an application for a Design Development Option (DDO) (UDC 3.11.1).
This site is located in the R-2 zone (UDC 4.7.9). A single-family residence (SFR) is a permitted use in this zone (Table 4.8-2). See Use-Specific Standards 4.9.7.B.5 - 9. 10.
The minimum setback is the greater of six (6) feet, or two-thirds (2/3) the height of the structure's wall facing each interior property line (Table 6.3-2.A).
Per the plot plan drawing specifically for Parcel 1, the building setbacks from the proposed north and west lot lines do not meet the minimum interior building setbacks as noted above.
1. The east and west elevations are dimensioned as 11.5' from the FFE. The height shall be measured from design grade next to the wall. For purposes of providing information for the building setback 8 inches have been added to the labeled height of 11.5'" which equals 12.17' from grade. The minimum building setback along the new west lot line must be 8.10' from the west wall to the new west lot line. The owner is proposing a building setback of 4.0'. (A DDO is required for the proposed reduced west building setback.)
2. The north and south elevations are dimensioned as 11.3' from the FFE. The height shall be measured from design grade next to the wall. For purposes of providing information for the building setback 8 inches have been added to the labeled height of 11.3'" which equals 11.96' from grade. The minimum building setback from the northeast wall of the building along the new north lot line must be 7.96'. The attached storage structure appears to have a maximum height of 8' facing the north lot line the minimum building setback must be 6'. The owner proposes 4.67' from the storage structure and northeast wing of the building to the new north lot line of parcel 1. (A DDO is required for the proposed reduced north building setback.)
02/25/2020 LOREN MAKUS ENGINEERING REVIEW Reqs Change Once the DDO and plot plans are approved, engineering can approve.
Floodplain compliance required for the new structure.
02/26/2020 SBEASLE1 ZONING-RECORDATION REVIEW Reqs Change LAND SPLIT PLAN
RETURNED FOR CORRECTIONS NOTICE
A resubmittal with a Comment Response Letter is required.

OVER-THE-COUNTER REVIEWS
1. May be available for some City reviews - at the City staffs discretion
2. Before visiting the City office, please contact the reviewers via phone or email
3. For contact information, see the reviewer's comments in PRO: www.tucsonaz.gov/pro.
4. PDSD hours: https://www.tucsonaz.gov/pdsd/contact-us-hours-service
5. Sign in at the receptionist desk (computer)

PERMIT: S19-088
For faster service, please enter this number in the Filedrop's "Project Description" field and on correspondence.

DESCRIPTION: LAND SPLIT - 1115 E. Blanton Drive.

FEE BALANCE: $0 (zero)
SEE REVIEWER'S COMMENTS and your submitted documents on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, left side, Activity Search, enter the Activity Number
- Permits section, click on blue tab
- Documents section, click on blue icon to the right of each document
- Reviews section, click on "Review Details"

YOUR NEXT STEPS: Submit the following items to the Filedrop - https://www.tucsonaz.gov/file-upload-pdsd
(In the Project Description field, enter the Activity Number.)
1) Comment Response Letter (your response to the reviewer's Requires Change comments)
2) Any other items requested by reviewers

After your resubmittal, the Land Split Plan will enter a new 5-working-day review cycle.
Thank you.
Sharon Beasley, Permit Specialist

City of Tucson
Planning and Development Services
Attn: Permit Counter/Payments
201 N. Stone Avenue, 3rd Floor
Tucson, AZ 85701
email: COTDSDPermits@TucsonAz.gov

Final Status

Task End Date Reviewer's Name Type of Review Description
02/26/2020 SBEASLE1 OUT TO CUSTOMER Completed