Plan Number: S19-041
Parcel: Unknown

Review Status: Completed

Review Details: LOT SPLIT REVIEW

Plan Number - S19-041
Review Name: LOT SPLIT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/18/2019 SBEASLE1 START PLANS SUBMITTED Completed
06/19/2019 KEN VAN KARSEN BUILDING-RESIDENTIAL REVIEW Reqs Change PLAN REVIEW COMMENTS

Roof projections may not extend to a point closer than 2 feet from the property line. Provide a building permit application and plan showing compliance with R302.1 (City of Tucson Amended) by removing the roof overhang along the new property line, or provide one-hour fire-resistive construction on the underside. If you have any questions please contact:

Ken Van Karsen
(520) 837-4912
City of Tucson Residential Plan Review
06/19/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change Independent water services and sewer connections are required for the two proposed lots.
06/19/2019 SBEASLE1 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Approved Tucson Water approves this lot split.
Thank you,
Ray Munoz
06/19/2019 LOREN MAKUS ENGINEERING REVIEW Approved
07/01/2019 SSHIELD1 H/C SITE REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Steve Shields
Section Manager

PROJECT: 9234 E Calle Maria
S19-041
Land Split (1st Review)

TRANSMITTAL DATE: July 1, 2019

1. The land split plans and documents have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Based on the provided plan it does not appear that the existing structure will meet perimeter yard setback requirements. Per Unified Development Code (UDC) Table 6.3-2.A: DIMENSIONAL STANDARDS FOR THE R-1, R-2, R-3, MH-1, & MH-2 ZONES the required perimeter yard setback is 6'-0" or 2/3 Height of the proposed exterior building wall. As no building elevations were provided Zoning cannot provide the required UDC comments for the Design Development Option (DDO). Provide building elevation with the next submittal. Until the DDO is submitted and approved the Land Split cannot be approved.

3. Based on the most current aerial photos of this site there are accessory structures located on the proposed southern lot. Per UDC Article 6.6.2.B accessory structures shall only be built on a lot occupied by a principal building. Review of our permitting system does not show that demolition permits have been issued.

4. Until all other review agencies have approved the land split zoning cannot approve.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
07/02/2019 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Steve Shields
Section Manager

PROJECT: 9234 E Calle Maria
S19-041
Land Split (1st Review)

TRANSMITTAL DATE: July 1, 2019

1. The land split plans and documents have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Based on the provided plan it does not appear that the existing structure will meet perimeter yard setback requirements. Per Unified Development Code (UDC) Table 6.3-2.A: DIMENSIONAL STANDARDS FOR THE R-1, R-2, R-3, MH-1, & MH-2 ZONES the required perimeter yard setback is 6'-0" or 2/3 Height of the proposed exterior building wall. As no building elevations were provided Zoning cannot provide the required UDC comments for the Design Development Option (DDO). Provide building elevation with the next submittal. Until the DDO is submitted and approved the Land Split cannot be approved.

3. Based on the most current aerial photos of this site there are accessory structures located on the proposed southern lot. Per UDC Article 6.6.2.B accessory structures shall only be built on a lot occupied by a principal building. Review of our permitting system does not show that demolition permits have been issued.

4. Until all other review agencies have approved the land split zoning cannot approve.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
07/02/2019 SBEASLE1 ZONING-RECORDATION REVIEW Reqs Change LAND SPLIT PLAN RETURNED FOR CORRECTIONS NOTICE
The reviews have been completed and a resubmittal is required.
Fee Balance: $99.00 (see the Balance column in the image below).
Prior to the completion of the next review, we require payment of the total fees (or the Review fees at a minimum). You may pay in person at the City of Tucson permit counter (Mon-Fri, 8:00 AM to 2:00 PM) or mail a check payable to the City of Tucson (see address below). Please write your Activity Number on the check.
Activity Number: S19-041
Project Description: LAND SPLIT / DDO - 9234 E. Calle Maria, resplit into two parcels.
For review comments, visit PRO at www.tucsonaz.gov/PRO, then search by Activity Number.
(If information isn't shown yet, check back later as data flows to PRO periodically throughout the day.)
Submit the following items to the PDSD Filedrop at https://www.tucsonaz.gov/file-upload-pdsd.
In the Project Description field, please include the Activity Number.
1) Comment Response Letter (states how all reviewer comments were addressed)
2) Any other items requested by reviewers
After resubmittal, the Plan will re-enter the 5-working-day Land Split review cycle.
Thank you.
Sharon Beasley, Permit Technician

City of Tucson
Planning and Development Services
Attn: Permit Counter/Payments
201 N. Stone Avenue, First Floor
Tucson, AZ 85701

Final Status

Task End Date Reviewer's Name Type of Review Description
07/02/2019 SBEASLE1 OUT TO CUSTOMER Completed