Plan Number: S08-067
Parcel: Unknown

Review Status: Completed

Review Details: FINAL PLAT PACKAGE

Plan Number - S08-067
Review Name: FINAL PLAT PACKAGE
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/11/2009 PGEHLEN1 START FINAL PLAT PACKAGE Completed
06/16/2009 LOREN MAKUS ENGINEERING REVIEW Approved Leave mylar package with H/C for review 6/11 and returned the same day. Approved.
06/16/2009 LOREN MAKUS ENGINEERING REVIEW Approved Leave mylar package with zoning for review 6/12 and returned the same day. Approved.
06/16/2009 LOREN MAKUS ENGINEERING REVIEW Approved Leave mylar package with engineering for review on 6/12 and returned 6/16 - approved.
06/16/2009 LOREN MAKUS ENGINEERING REVIEW Approved Leave mylar package with engineering administrator for review on 6/16 and returned 6/18 - denied.
06/16/2009 LOREN MAKUS ENGINEERING REVIEW Approved Leave mylar package with engineering reviewer to summarize engineering administrator's comments on 6/18.
06/19/2009 JIM VOGELSBERG ENGINEERING PROCESSING Denied Leave mylar package with H/C for review 6/11 and returned the same day. Approved.
06/19/2009 JIM VOGELSBERG ENGINEERING PROCESSING Denied Leave mylar package with zoning for review 6/12 and returned the same day. Approved.
06/19/2009 JIM VOGELSBERG ENGINEERING PROCESSING Denied Leave mylar package with engineering for review on 6/12 and returned 6/16 - approved.
06/19/2009 JIM VOGELSBERG ENGINEERING PROCESSING Denied Leave mylar package with engineering administrator for review on 6/16 and returned 6/18 - denied.
06/19/2009 JIM VOGELSBERG ENGINEERING PROCESSING Denied Leave mylar package with engineering reviewer to summarize engineering administrator's comments on 6/18.
06/19/2009 BEVERLEY HESTER ENGINEERING ASSIGN REVIEW Completed Leave mylar package with H/C for review 6/11 and returned the same day. Approved.
06/19/2009 BEVERLEY HESTER ENGINEERING ASSIGN REVIEW Completed Leave mylar package with zoning for review 6/12 and returned the same day. Approved.
06/19/2009 BEVERLEY HESTER ENGINEERING ASSIGN REVIEW Completed Leave mylar package with engineering for review on 6/12 and returned 6/16 - approved.
06/19/2009 BEVERLEY HESTER ENGINEERING ASSIGN REVIEW Completed Leave mylar package with engineering administrator for review on 6/16 and returned 6/18 - denied.
06/19/2009 BEVERLEY HESTER ENGINEERING ASSIGN REVIEW Completed Leave mylar package with engineering reviewer to summarize engineering administrator's comments on 6/18.
07/02/2009 PGEHLEN1 CDRC STAFF CITY AGENDA OFFICE Passed
07/02/2009 PGEHLEN1 CDRC STAFF CITY CLERK'S OFFICE Passed