Plan Review Detail
Review Status: Completed
Review Details: REVISION - TENT PLAT & CORE RESUB
Plan Number - S07-033
Review Name: REVISION - TENT PLAT & CORE RESUB
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/28/2016 | KROBLES1 | START | PLANS SUBMITTED | Completed | |
| 10/07/2016 | PAUL BAUGHMAN | ENGINEERING | REVIEW | Approved | Please note for the record that the applicant acknowledged routing 57 cfs to two 24" diameter culverts instead of the two 36" diameter culverts further to the north where 50 cfs is being conveyed. Comment response referenced headwater calculations that were supposed to be found in appendix D. Only tail water data was found in this appendix. Internal staff calculations were run independantly and it was found that a little over 10 cfs is conveyed over the road at the location with the two 24" diameter culverts in a 100 year storm. |
| 10/10/2016 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/12/2016 | KROBLES1 | OUT TO CUSTOMER | Completed |