Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Plan Number: S05-244
Parcel: Unknown

Address:
3164 E 4TH ST

Review Status: Completed

Review Details: FINAL PLAT PACKAGE

Plan Number - S05-244
Review Name: FINAL PLAT PACKAGE
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/28/2008 CDRC1 START FINAL PLAT PACKAGE Completed
04/28/2008 LAITH ALSHAMI ENGINEERING ASSIGN REVIEW Completed DATE: April 28, 2008
SUBJECT: Fourth Street RCP Final Plat Submittal- 3rd Engineering Review
TO: Patricia Gehlen, CDRC Manager
LOCATION: 3164 E 4th Street, T14S R14E Sec 09 Ward 6
REVIEWERS: Jason Green, CFM
ACTIVITY: S05-244


SUMMARY: Engineering Division of Development Services Department has received the Mylar Sheet of the proposed Final Plat, a copy of the original CC&R's, and a copy of the original Assurance Package. Engineering Division has reviewed Final Plat Mylar, CC&R's and Assurance Package and recommends approval of the Final Plat at this time


If you have any questions, or to schedule a meeting, I can be reached at 837-4929.


Jason Green, CFM
Senior Engineer Associate
Engineering Division
COT Development Services
04/28/2008 JASON GREEN ENGINEERING REVIEW Approved DATE: April 28, 2008
SUBJECT: Fourth Street RCP Final Plat Submittal- 3rd Engineering Review
TO: Patricia Gehlen, CDRC Manager
LOCATION: 3164 E 4th Street, T14S R14E Sec 09 Ward 6
REVIEWERS: Jason Green, CFM
ACTIVITY: S05-244


SUMMARY: Engineering Division of Development Services Department has received the Mylar Sheet of the proposed Final Plat, a copy of the original CC&R's, and a copy of the original Assurance Package. Engineering Division has reviewed Final Plat Mylar, CC&R's and Assurance Package and recommends approval of the Final Plat at this time


If you have any questions, or to schedule a meeting, I can be reached at 837-4929.


Jason Green, CFM
Senior Engineer Associate
Engineering Division
COT Development Services
05/02/2008 LAITH ALSHAMI ENGINEERING PROCESSING Completed DATE: April 28, 2008
SUBJECT: Fourth Street RCP Final Plat Submittal- 3rd Engineering Review
TO: Patricia Gehlen, CDRC Manager
LOCATION: 3164 E 4th Street, T14S R14E Sec 09 Ward 6
REVIEWERS: Jason Green, CFM
ACTIVITY: S05-244


SUMMARY: Engineering Division of Development Services Department has received the Mylar Sheet of the proposed Final Plat, a copy of the original CC&R's, and a copy of the original Assurance Package. Engineering Division has reviewed Final Plat Mylar, CC&R's and Assurance Package and recommends approval of the Final Plat at this time


If you have any questions, or to schedule a meeting, I can be reached at 837-4929.


Jason Green, CFM
Senior Engineer Associate
Engineering Division
COT Development Services
06/17/2008 MARILYN KALTHOFF CDRC STAFF CITY AGENDA OFFICE Completed
06/17/2008 MARILYN KALTHOFF CDRC STAFF CITY CLERK'S OFFICE Completed