Plan Number: S05-088
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW

Plan Number - S05-088
Review Name: RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/06/2006 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Review, 01/06/2005

SUBJECT: Sierra Morado Unit 2
S05-088, T15S, R15E, SECTION 12

RECEIVED: Tentative Plat, Landscape Plan and Drainage Report on December 27, 2005

The subject project has been reviewed. We offer the following comments:

Drainage Report:

1. The Mesquite Wash erosion hazard setback line is shown on Figure 3 encroaching on lots 228- 239. Since these lots will be protected from potential erosion, the setback should be shown behind the erosion protection line.
2. The proposed runoff of 67 cfs at Concentration point 13a is a deviation from the requirements of Development Standard 3-01.4.4.B., which requires a Development Standard Modification Request (DSMR). The explanation/justification for this proposed deviation that was presented in the response letter can be used in the DSMR application.

Tentative Plat/Development Plan:

1. A revised Mitigation Report, for the proposed encroachment on Mesquite Wash 50' study area, has not been included in the last Tentative Plat submittal. Submit a revised Mitigation Report.
2. The email that was mentioned in the response letter dated October 27, 2005, concerning the Bilby Road proposed cross section minor revision, has not been attached to this resubmittal.
3. The 10' slope and water ponding setback has not been shown on all proposed basins. Additionally, the 10' setback needs to be called out as such in order to prevent field modifications that might result in reducing the setback.
4. It is not clear why the Mesquite Wash Riparian Habitat area is depicted on the Tentative Plat. It appears that it does not have any significant benefit to the Tentative Plat review. Verify the need for this information and revise as necessary.
5. Revise the Tentative Plat according to the Drainage Report revisions.

Prepare a detailed response that explains the revisions that were made and references the exact location in the drainage report and on the Tentative Plat where the revisions were made.



RESUBMITTAL REQUIRED: Revised Tentative Plat and Drainage Report
01/06/2006 DAN CASTRO ZONING REVIEW Approv-Cond COMMENTS:

The Zoning Review Section approves the tentative plat for this subdivision, subject to the following changes on the executed tentative plat. However, should there be any changes requested by other CDRC members, the Zoning Review Section approval is void, and we request copies of the revised tentative plat to verify that those changes do not affect any zoning requirements.

1.
WASH application shall be submitted and approved prior to tentative plat approval. A copy of the approved WASH application must be submitted with the mylars.

2. Provide a copy of the letter signed by the DSD director approving the change to the Bilby Road street section. The signed letter shall be submitted with the mylars.

If you have any questions about this transmittal, please call Dan Castro at (520) 791-5550.
01/11/2006 JOE LINVILLE LANDSCAPE REVIEW Denied 1) Page 7 of the tentative plat includes a channel within the 50' study area adjacent to the Civano Wash. A seperate application will be required for any study area development.

2) A revised wash report was not received with this submittal. The wash report for mesquite wash is to include the drainage work shown on sheet 6 of the tentative plat and deal with the subject of trails located within the study area.

3) A revised wash report was not received with this submittal. Include "Mesquite Wash (proposed WASH)" on the cover of the report.

4) A revised wash report was not received with this submittal. The development proposed within the resource area is not compatible with the purpose and intent of these regulations. The proposed development in the Mesquite Ranch WASH study area within or adjacent to Lots 228-235 & 238-239 has not been justified. Other areas are under consideration. The applicant is required to demonstrate why the resource area cannot be left in its natural condition. The Landscape Section finds that:
A) granting an approval may harm remaining Resource Areas.
B) approval would not afford protection of, and opportunities for restoration of, existing riparian vegetation.
C) there is no proof submitted that failure to grant an approval will pose an exceptional hardship to the property owner or developer.

Resubmittal of all plans is required. The irrigation plan must be approved by the TDOT Landscape Architect.
01/12/2006 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

January 12, 2006

Pattie Davis
MMLA Psomas
800 East Wetmore Road, Suite 110
Tucson, AZ 85718

Subject: S05-088 Sierra Morado Unit 2 Tentative Plat

Dear Patti:

Your submittal of December 27, 2005 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLUELINES MUST BE FOLDED

3 Copies Revised Tentative Plat (landscape, engineering, DSD)

3 Copies Revised Landscape Plan (engineering, landscape, DSD)

2 Copies Revised Drainage Report (engineering, DSD)



Should you have any questions, please call me at 791-5608, ext 1179.

Sincerely,


Patricia Gehlen
CDRC Manager

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/

Via fax: 292-1290
12/23/2005 FERNE RODRIGUEZ START PLANS SUBMITTED Completed