Plan Number: S05-052
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - FINAL PLAT REVIEW

Plan Number - S05-052
Review Name: RESUBMITTAL - CDRC - FINAL PLAT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/05/2007 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
09/24/2007 GLYNDA ROTHWELL UTILITIES TUCSON ELECTRIC POWER Denied SUBJECT: BARRIO PANTANO
S05-52

TEP is unable to approve the plat at this time, in order to approve the
final plat the following is required:


* Depict the existing Right of Way Easement granted to TEP,
recordedin Docket 11418 at Page 383.
* Delete the word FOR from the third paragraph of the paragraph to
read as: "I HEREBY GRANT TO THE PUBLIC AND ALL UTILITY COMPANIES ALL
EASEMENTS AS SHOWN HEREON FOR THE PURPOSES OF ACCESS, INSTALLTION AND
MAINTENANCE OF PUBLIC SEWERS AND UTILTIES AND OTHER USES AS DESIGNATED
BY THIS PLAT."

Liza Castillo, Right of Way Agent
Tucson Electric Power Co.
Unisource Energy Services
offc-(520) 917-8745
fax-(520) 545-1416
lcastillo@tep.com

-----Original Message-----
From: Kent A. Delph [mailto:kadelph@greniereng.com]
Sent: Friday, September 07, 2007 9:26 AM
To: Paul Machado ; Castillo, Liza
Cc: Patricia Gehlen ; Ferne Rodriguez; Jan Fischer ; Katrina
Ridgway; Ernie Duarte
Subject: S05-052: Final Plat Submittal and Potential Tentative
Plat Expireation



Paul and Liza,



I believe Patricia Gehlen has indicated to me the Tentative Plat
(TP) will expire on the referenced project next week on the 12th. The
project changed owners (which delayed many things on our end and is not
a function of the City review at all) and the Final Plat was resubmitted
Sept 4th to address the last comments which were for the assurance
package and TEP review.



These items have been addressed. If there is any way this
project could be shuffled up a bit it would be greatly appreciated as we
would like to avoid expiration of the TP.



I realize this is very late for this request, but anything would
be appreciated. I also understand it may be unrealistic and City Code
may have to let the TP expire.



Thanks,



Kent A. Delph, P.E.

Vice President

Grenier Engineering Inc.

1660 N. Alvernon Way

Tucson, AZ 85712

ph.520.326.7082

fx. 520.326.7508



CONFIDENTIALITY NOTICE
This e-mail transmission, and any documents, files or previous
e-mail messages attached to it may contain information that is
confidential or legally privileged. If you are not the intended
recipient, or a person responsible for delivering it to the intended
recipient, you are hereby notified that you must not read this
transmission and that any disclosure, copying, printing, distribution or
use of any of the information contained in or attached to this
transmission is STRICTLY PROHIBITED. If you have received this
transmission in error, please immediately notify the sender by telephone
or return e-mail and delete the original transmission and its
attachments without reading or saving in any manner. Thank you.



ELECTRONIC FILES

Electronic files are non-certified recordings of printed
documents prepared by Grenier Engineering, Inc. and are not part of the
contract documents. These files are provided only for the convenience
of the receiving party for the purposes expressly authorized. In
accordance with standard industry practice, only printed copies of
documents conveyed to you by Grenier Engineering, Inc. may be relied
upon. Any use of the information obtained or derived from these files
will be at the receiving party's sole risk and shall be in accordance
with the contract signed between the receiving party and Grenier
Engineering Inc. Because data stored in electronic media format can
deteriorate or be modified inadvertently or otherwise without
authorization of the data's creator, the receiving party agrees that it
has the obligation to perform acceptance tests prior to using any of the
data. Upon use of this data, receiving party shall be deemed to have
accepted the data thus transferred. Please check this disk/file(s) for
virus contamination prior to use. These drawings remain the
intellectual property / copyright of Grenier Engineering, Inc. and shall
not be used for any other project other than the location / client for
which it was created.
09/27/2007 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES



Kent Delph
Delph Engineering
221 North Court #103
Tucson, AZ 85701

Subject: S05-052 Barrio Pantano Final Plat

Dear Kent:

Your submittal of September 5, 2007 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLUELINES MUST BE FOLDED

2 Copies Revised Final Plat (TEP, DSD)






Should you have any questions, please call me at 837-4919.

Sincerely,


Patricia Gehlen
CDRC Manager