Plan Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW
Plan Number - S05-030
Review Name: RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/07/2006 | DAVID RIVERA | ZONING | REVIEW | Approv-Cond | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: David Rivera Principal Planner PROJECT: S05-030 Cantera Tentative Plat TRANSMITTAL DATE: January 7, 2006 DUE DATE: December 22, 2006 COMMENTS: 1. The Zoning Review Section approves the tentative plat for this subdivision, subject to the following changes on the executed tentative plat. However, should there be any changes requested by other CDRC members, the Zoning Review Section approval is void, and we request copies of the revised tentative plat to verify that those changes do not affect any zoning requirements. 2. It appears that the required access between the Cantera development and the development to the south has not been depicted on the drawing. It may be necessary to add a detail drawing depicting the proposed intersection as required per rezoning case C9-04-15, rezoning condition # 1. It is acknowledged that both Roger and I signed an ok by general notes 33 and 34 but I believe it is necessary to depict the proposed intersection even if it is not to be built by the Cantera developer. Please confer with Roger Howlett as to how to proceed with this requirement. If you have any questions about this transmittal, please call David Rivera, (520) 791-5608. C:\planning\cdrc\tentativeplat\S05030tpca.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised tentative plat |
01/12/2006 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Approv-Cond | COMMUNITY DESIGN REVIEW COMMITTEE DEVELOPMENT SERVICES February 2, 2006 Wocky Redstar Castro Engineering Corp 3580 West Ina Road, Suite 200 Tucson, AZ 85741 Subject: S05-030 Dos Rios Tentative Plat Dear Wocky : The above referenced plan has been CONDITIONALLY APPROVED by the Community Design Review Committee, subject to the revisions required on the mylars. Please submit the following documents for sign-off. 1 Reproducible Oce or Photo Mylar copy of the Plat, landscape plan and NPPO. Should you have any questions, please call me at 791-5608, ext 1179. Sincerely, Patricia Y. Gehlen CDRC Manager All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/ Via fax: 293-2115 |
12/08/2005 | FERNE RODRIGUEZ | START | PLANS SUBMITTED | Completed | |
12/21/2005 | ELIZABETH EBERBACH | ENGINEERING | REVIEW | Approved | DATE: December 21, 2005 TO: Patricia Gehlen; CDRC Coordinator SUBJECT: Dos Rios (Cantera) Tentative Plat 3RD Resubmittal Engineering Review LOCATION: T15S R14E Section 10 REVIEWER: Elizabeth Eberbach ACTIVITY NUMBER: S05-030 SUMMARY: The revised Tentative Plat and response letter were received by Engineering on December 9, 2005. Engineering has met with the consultants, reviewed the received items and the letter from Sierra Pacific regarding offsite temporary construction. Any mitigation for the differential grading shall be addressed at grading plan review stage. The Real Estate Division has requested that they need to be contacted at least one month before final plat is scheduled on M&C agenda, and that the vacation of Antrim Loop must be on the same agenda. Engineering recommends approval of the Tentative Plat. The Drainage Report dated was accepted for review for Tentative Plat purposes only. Call me at 791-5550, extension 2204, if you have any questions. Elizabeth Eberbach, PE Civil Engineer Engineering Division Development Services |
12/23/2005 | ROGER HOWLETT | COT NON-DSD | COMMUNITY PLANNING | Approv-Cond | DEPARTMENT OF URBAN PLANNING & DESIGN Regarding SUBJECT: Community Design Review Committee Application CASE NUMBER: CASE NAME: DATE SENT S05-030 Cantera (AKA Dos Rios) 12/22/05 (XXXX) Tentative Plat () Development Plan (XXXX) Landscape Plan () Revised Plan/Plat () Board of Adjustment (XXXX) Other – NPPO Plan CROSS REFERENCE: C9-04-15 NEIGHBORHOOD PLAN: General Plan GATEWAY ROUTE: COMMENTS DUE BY: 12/22/05 SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS: () No Annexation or Rezoning Conditions, Not an RCP - No Comment () Proposal Complies with Annexation or Rezoning Conditions () RCP Proposal Complies With Plan Policies () See Additional Comments Attached () No Additional Comments- Complies With Planning Comments Submitted on: (XXXX) Resubmittal Required: (XXXX) Tentative Plat () Development Plan () Landscape Plan REVIEWER: DCE 791-4505 DATE: 12/20/05 Department of Urban Planning and Design Comments S05-030 Cantera (AKA Dos Rios) December 22, 2005 Please correct tentative plat to be in compliance with C9-04-15, rezoning condition # 1 which required the tentative plat to be in substantial compliance with the preliminary development plan dated September 9, 2004. Atrim Loop does not provide cross-access to the residential interior of Desert Point 2, the remainder of the rezoning site to the south. Per the preliminary development plan approved through the rezoning process, a connection to the south of this rezoning site will provide direct access onto both Alvernon Way and Benson Highway. Also please make a note of this under the General Notes Section. |
12/23/2005 | ROGER HOWLETT | COT NON-DSD | COMMUNITY PLANNING | Approv-Cond | DEPARTMENT OF URBAN PLANNING & DESIGN Regarding SUBJECT: Community Design Review Committee Application CASE NUMBER: CASE NAME: DATE SENT S05-030 Cantera (AKA Dos Rios) 01/18/06 (XXXX) Tentative Plat () Development Plan (XXXX) Landscape Plan () Revised Plan/Plat () Board of Adjustment (XXXX) Other – NPPO Plan CROSS REFERENCE: C9-04-15 NEIGHBORHOOD PLAN: General Plan GATEWAY ROUTE: COMMENTS DUE BY: N/A SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS: () No Annexation or Rezoning Conditions, Not an RCP - No Comment (XXXX) Conditionally Approved* *NOTE: Development Services staff to check mylar on Sheet One of Six for note confirming future right-of-way connection to Desert Point Est. at Antrim Loop and Tappen Drive as shown on Sheet Five of Six. REVIEWER: DCE 791-4505 DATE: 1/17/06 |