Plan Number: S04-053
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - FINAL PLAT REVIEW

Plan Number - S04-053
Review Name: RESUBMITTAL - CDRC - FINAL PLAT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/23/2005 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
08/26/2005 KAY MARKS PIMA COUNTY ADDRESSING Denied 201 N. STONE AV., 1ST FL
TUCSON, AZ 85701-1207

KAY MARKS
ADDRESSING OFFICIAL
PH: 740-6480
FAX #: 740-6370


TO: CITY PLANNING
FROM: KAY MARKS, ADDRESSING OFFICIAL
SUBJECT: S04-053 RIO NUEVO MERCADO DISTRICT/REVISED FINAL PLAT
DATE: August 26, 2005



The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and the following matters must be resolved prior to our approval:


Change McGee to McKee on Location Map.

Change Panorama Est 9/80 to 9/86 on Location Map.

Change South Menlo Park 3/113 to 3/131 on Location Map.

Add Grove to Cottonwood on Location Map.

Spanish approval for Avenida del Convento is still needed.

Change the prefixes of Calle de los Zanjeros (add the s) and Calle de los Chapulines. Calle is reserved for true east-west streets.






jg
08/26/2005 FRODRIG2 COT NON-DSD REAL ESTATE Denied Page #1; Add to the City's signature line under the dedication:

"Dedications of City owned property shown herein and abandonment of the City's interest in the easements being abandoned by this plat have been approved and authorized by the adoption of Ordinance # ."

This Ordinance will give the Mayor authority to sign the plat and the Ordinance number will be filled in by the Clerk prior to recording.

Page #3; Ingress Egress easement crossing portions of Blocks 2 and 3 has been removed from this submittal. Why? Our previous comments recommended this read "to be abandoned by this plat"

Remove the statement "Ingress egress easement by separate instrument" on the Calle De Los Chapulines R/W.

Page #4 & #5; The notes for the existing easements per Dk 5524 Pg 501 need to be modified. The easements have been partially abandoned by Dk 12615 Pg 1932 (as to the I/E portion only). Unfortunately this document will need to be rerecorded to address the sewer portion of the easement. Real Estate is working on that.

Why is Lot 100 circled?
08/29/2005 GLYNDA ROTHWELL UTILITIES TUCSON ELECTRIC POWER Denied SUBJECT: RIO NUEVO MERCADO DISTRICT (MENLO PARK)
Lots 1-100, Commercial Blocks, "A", "B", "C" & "D"
S04-053

Tucson Electric Power Company (TEP) has reviewed the final plat submitted
for review August 23, 2005. TEP is unable to approve the plat at this time.

In order for this Company to approve the final plat, the following is
required.

* A 10' x 10' TEP easement is required at each of the transformers
that are not located within common area.
* A 10' x 10' TEP easement is required at the junction cabinet to be
located at Lot 70.
* A 6' x 6' TEP easement is required at the pedestal to be located on
Lots 73 & 74.
* Add the following statement to the dedication:

"AN EASEMENT IS GRANTED FOR THE PURPOSE OF ACCESS, INSTALLATION, REPLACING,
REPAIRING AND MAINTENANCE OF ELECTRICAL METERS, CABLE AND CONDUITS, WHICH
GROUPED ELECTRICAL METERS ARE ATTACHED TO THE EXTERIOR WALLS."

Show all requested easements and dedication on the resubmittal of the final
plat. Submit two bluelines to the City of Tucson for TEP's final approval.

Please contact me at (520) 917-8745 if you have any questions.


Liza Castillo
Right of Way Agent
Land Management
Tucson Electric Power Co.
(520) 917-8745
lcastillo@tep.com <mailto:lcastillo@tep.com>
09/08/2005 ELIZABETH EBERBACH ENGINEERING REVIEW Denied TO: Patricia Gehlen; CDRC Coordinator
SUBJECT: Rio Nuevo Mercado Final Plat Re-submittal Engineering Review
LOCATION: T14S R13E Section 14
REVIEWER: Elizabeth Eberbach
ACTIVITY NUMBER: S04-053

SUMMARY: The revised Final Plat, CC&R's , and portions of the assurance package were received by Engineering on August 23, 2005. Engineering has reviewed the received items and does not recommend approval of the Final Plat at this time. The biggest engineering issue at this time for this plat is the proposal to relocate or abandon existing easements; unless this issue is addressed promptly the plat may not proceed to Mayor and Council.

FINAL PLAT COMMENTS:
1) City of Tucson Development Standards (DS) Section No.7-01.4 and DS Sec.2-03.2.3.C: There are easements indicated throughout the plat as abandoned by separate instrument. In some cases these easements are shown to cross proposed lot locations, which conflicts with the status of the easement. The easements shall have a docket and page indicating that they are extinguished prior to approval of the Final Plat. Abandonments of the easements are required for the Final Plat approval. Clarify which utility easements have existing utilities within them and provide copies of the utility letters of no interest / vacation. This comment has been provided throughout the tentative plat and final plat reviews and this issue has not been resolved. The time encountered to abandon easements can delay the scheduling of Final Plats for Mayor and Council.
2) DS Sec.2-03.6.4.A: Address the following other easement comments:
a) DS Sec.7-01.4.A: Per this section, the developer must obtain from each entity having a record interest in an easement, as shown by a current title report, a recordable document such as a quit-claim deed or abandonment of easement which relinquishes its interest in the easement. The request for abandonment should be made to the entity holding an easement interest shortly after the CDRC approval of the tentative plat. This is in order to allow adequate time for relocation of any facilities within the easement prior to abandonment and depiction of the new easement on the final plat. As stated in prior comment letters and meetings, it is imperative that the status of the utilities easements within this project is clarified. Submit letters of agreement or no interest from any utility (or other) entity listed as an interest to any of the utility easements intended to be abandoned. Then label the docket and page on the plat of each of the abandoned utility easements.
b) Explain purpose of described entities that are not newly within the Final Plat boundary: Paseo de la Cosecha, Landscape buffer shown on sheet 5. See note 23 - refers to Common Area and right-of-way - this is neither.
c) Assure all easements as listed in the Title Report and other documents are clearly drawn, labeled with Book/page or Docket/page, and/or listed as a blanket easement on the Final Plat. Label each street, alley, easement (type), and drainageway with the appropriate dedication notation. (Some of this dedication information is already being provided by Real Estate.) Specifically address the following:
i) Explain whether schedule B items 5, 6, and 7 are blanket easements.
ii) On sheet 3, label Paseo de la Cosecha label as public right of way.
iii) (In the response letter, it was stated that this had been done, yet there are no docket/pages for the proposed abandonments of the following utilities.) On sheets 4&5, label dkt/pg for vacation/abandonment of:
(1) "Existing 30' Public Utility Easement and Sewer Easement"
(2) "Existing 10' Electric Esmt"
(3) "Existing 20' Sewer Easement"
(4) "Existing 50' Ingress/Egress Easement" - explain why is this showing if "not on Title Report".
3) DS Sec.2-03.6.5.C.5: Address the following boundary data / survey comments:
a) Since Paseo de la Cosecha and Calle de Los Chapulines are a part of the plat, provide width, curve, and other line data.
b) DS Sec.2-03.6.5.A: Clarify which corner is used for corner tie recordation information on the plat.
c) DS Sec.2-03.6.5.C.3: Provide closure sheet for project boundary.
4) DS Sec.2-03.6.1.D.2: On the location map on sheet 1, identify subdivision (i.e. Rio Nuevo Blks 1-5); referencing recorded subdivision plats by book and page numbers.
5) DS Sec.2-03.6.1.L: Identify corner monuments as existing, or proposed to be set by RLS. This may be clarified in the legend.
6) DS Sec.2-03.6.4.H: Show no-vehicular access easements at entrance/exits to Common Areas "C". Also, correct discrepancies for Common Area labels that do not match project layout.
7) DS Sec.2-03.6.5.C.6: On sheet 5, clarify street monuments for Clearwater Drive, if a part of this plat. Specifically, show survey street monuments to be set in Clearwater from new public right-of-ways: Avenida Del Palo Fierro, Calle de Los Higos, and Calle de Los Zanjero.
8) DS Sec.2-03.6.2.A: Regarding General Note 4, clarify whether the total acreage for the plat, including the blocks, is 13.571 acres.
9) DS Sec.2-03.6.3.C: Under Dedication section on sheet 1, under beneficiary, provide the developer's contact name.
10) DS Sec.2-03.6.6: Address the following CC&R comments:
a) Provide an original, signed copy of the CC&R's.
b) Per Standards Manual for Drainage Design and Floodplain Management section 14.3.2, the drainage area maintenance and responsibility verbiage from DS Sec.10-02.14.3.2.a-d & 10-02.14.3.3 must be included on the CC&R's, or placed on the Final Plat.
c) Also, the CC&R's shall provide the list of maintenance recommendations for the drainage areas as outlined in the Drainage Report or as provided by the engineer and accepted by the City of Tucson DSD Engineer.
11) DS Sec.2-03.7.1.G: The final plat cannot be scheduled for Mayor and Council consideration until the financial assurances are approved. Address the following assurance package comments:
a) Address comment 2g above regarding description for Common Area "A". All descriptions for all documents (CC&R's, Assurances, and Title Block) shall match. Please be aware that the legal office may reject assurance paperwork if the verbiage does not match exactly the verbiage on the Final Plat's Title Block.
b) Provide revised AGREEMENT TO CONSTRUCT SUBDIVISION IMPROVEMENTS / THIRD PARTY TRUST, revising the list of assurable items that was submitted to include all assurable items specific to this project - an item should be added regarding compliance with Landfill Ordinance.
c) All portions of the revised assurance package shall be compiled and resubmitted as complete documents; pieces of the revised assurances will not be acceptable for resubmittal. Provide AGREEMENT TO CONSTRUCT, Trust Agreement, AMENDMENT TO TRUST / THIRD PARTY TRUST, and a copy of a sample Warranty Deed.

Submit revised Final Plat, complete assurance package, and complete response letter. A meeting is required to go over the assurance package. If you have any questions on the easement comments or other concerns, please call me at 791-5550 extension 2204.

Elizabeth Eberbach, PE
Civil Engineer
Engineering Division
Development Services
09/13/2005 DAVID RIVERA ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department Plans Coordination Office
FROM: David Rivera
Principal Planner

PROJECT: S04-053
Menlo Park Mercado District
Final Plat - (PAD)

TRANSMITTAL: 09/13/05

DUE DATE: 08/29/05

COMMENTS:

1. Section 4.1.7.3, LUC, permits a maximum of one year from the date of application to obtain approval of a final plat plat. If, at the end of that time, the final plat has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this final plat is February 10, 2006.

2. Please add to the title of the introduction sheet the proposed lot numbers, common area designations, and block designations associated with this plat.

Previous Comment: If applicable please clarify if CC&R's will be drawn up for the PAD development or is the PAD document intended to serve as the CC&R's. DS 2-03.6.6

3. On the last review I neglected to ask that the width for "Calle De Los Chapulines" be added to the plan.

It is my understanding from a meeting, which took place a few months ago that, the proposed roadway along the West Side of the subdivision was private property. I know that there was a requirement for a DSMR and that a DSMR could not be applied for because the proposed roadway is not only on private property but could not be dedicated as originally proposed because the proposed roadway is a one way PAAL for the adjacent development. I also acknowledge that this issue may take some time to resolve.

Zoning will require verification of all the above items to have been resolved before the final plat can be approved.

If you have any questions about this transmittal, please call David Rivera, (520) 791-5608.

DGR C:\planning\cdrc\finalplat\S04053fp2.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised final plat, CC&R's and additional requested documents.
09/17/2005 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

September 17, 2005

David Little
WLB Group
4444 East Broadway
Tucson, AZ 85711

Subject: S04-053 Rio Nuevo Mercado District Final Plat

Dear David:

Your submittal of August 23, 2005 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLUELINES MUST BE FOLDED

6 Copies Revised Final Plat (addressing, real estate, TEP, zoning, engineering, DSD)

3 Copies CC&R's (engineering, zoning, DSD)


Should you have any questions, please call me at 791-5608 ext. 1179.



Sincerely,


Patricia Y. Gehlen
CDRC Manager