Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: S03-025
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL - TENTATIVE PLAT REVIEW

Plan Number - S03-025
Review Name: RESUBMITTAL - TENTATIVE PLAT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/20/2004 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
02/23/2004 LAITH ALSHAMI ENGINEERING REVIEW Approved SUBJECT: Offices at Rillito Crossing
S03-025, T13S, R14E, SECTION 27

RECEIVED: Tentative Plat on February 20, 2004

The subject submittal has been reviewed. The Development Plan is acceptable and recommended for approval pertaining to Engineering and Floodplain.
03/03/2004 PETER MCLAUGHLIN ZONING REVIEW Approv-Cond CDRC TRANSMITTAL


TO: Development Services Center
Plans Coordination Office

FROM: Peter McLaughlin
Senior Planner

FOR: Patricia Gehlen
Principal Planner


PROJECT:
S03-025
Offices at Rillito Crossing
Tentative Plat/Development Plan

TRANSMITTAL: March 3, 2004
DUE DATE: March 4, 2004

The Zoning Review Section at Development Services verifies that the tentative plat meets the requirements of the Land Use Code, subject to the following requirement. However, should there be any changes requested by other CDRC members, the approval is void, and we request copies of the corrected tentative plat to verify that those changes do not affect any zoning requirements.

COMMENTS

1. Provide copies of the LDO approval documents for LDO-03-201. These are the copies that were stamped and signed by Frank Podgorski. One set of these LDO approval sheets must be placed in City records. The other set is to be kept by the applicant.

Should the CDRC recommend approval of the tentative plat, please have the applicant submit sign-off copies for approval.

If you have any questions about this transmittal, please call Peter McLaughlin, (520) 791-5608.
03/04/2004 JOE LINVILLE LANDSCAPE REVIEW Approv-Cond 1) The required minimum height of the parking lot screen along Paradise falls Drive is 5', rather than 3'. LUC Table 3.7.2-I, LUC 3.7.3.6.A.2
Revise the plan to specify a screen plant which provides the required screening. Revise all related notes as necessary.
There is currently no non-residential use across the street.
03/04/2004 JOE LINVILLE LANDSCAPE REVIEW Approv-Cond Please make corrections on mylars and make appointment to review before final submittal.
03/05/2004 ROGER HOWLETT COT NON-DSD COMMUNITY PLANNING Approved COMPREHENSIVE PLANNING TASK FORCE COMMENTS

Regarding

SUBJECT: Community Design Review Committee Application

CASE NUMBER: CASE NAME: DATE SENT

S03-025 Offices at Rillito Crossing 03/04/04

(X) Tentative Plat
() Development Plan
(X) Landscape Plan
() Revised Plan/Plat
() Board of Adjustment
() Other

CROSS REFERENCE: C9-1-30

NEIGHBORHOOD PLAN: Northside

GATEWAY/SCENIC ROUTE: NO

COMMENTS DUE BY: 3/04/04

SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS:

() No Annexation or Rezoning Conditions, Not an RCP - No Comment
(X) Proposal Complies with Rezoning Conditions
() RCP Proposal Complies With Plan Policies
(*)(X) See Additional Comments Attached (*)
() No Additional Comments - Complies With Planning Comments Submitted on:






(*) See comments on staff meeting held on 3/3/04

REVIEWER: msp 791-4505 DATE: 3/03/04

Comprehensive Planning Task Force Review
S03-025 – Offices at Rillito Crossing: Tentative Plat Review
March 3, 2004


Submittal dated February 20, 2004 is in compliance with rezoning C09-01-30. Staff reviewed submittal on March 3, 2004, to determine compliance of S03-025, Offices at Rillito Crossing, with rezoning requirements. In attendance were Any Dinauer, from the Department of Transportation, Jim Vogelsberg and Craig Gross, from the Department of Development Services and Manuel Padilla from the Comprehensive Planning Task Force Department. Specifically, staff held a meeting to review submittal for compliance with rezoning case C09-01-30, conditions # 4 & 5. These conditions deal with right-of-way requirements and improvements to Alvernon Way along the alignment of this development. It was determined at the meeting held March 3, 2004, by staff from the Department of Development Services Department and the Department of Transportation that this submittal is in compliance with rezoning conditions # 4 & 5.
03/10/2004 GLENN HICKS COT NON-DSD PARKS & RECREATION Approved DATE: March 10, 2004

TO: Ferne Rodriguez, Development Services

FROM: Glenn Hicks, Parks and Recreation

SUBJECT: CDRC Transmittal, Project S03-025 Offices at Rillitio Crossing: RTP 2/20/04

CC: Craig Gross, Development Services


Staff has approved the resubmitted(2/20/04) tentative plat.