Permit Review Detail
Review Status: Completed
Review Details: DEV PKG
Permit Number - DP22-0036
Review Name: DEV PKG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/04/2022 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 03/04/2022 | SBEASLE1 | ENGINEERING | REVIEW | Approved | Engineering was approved by Loren Makus during the OK to Submit. |
| 03/04/2022 | SBEASLE1 | UTILITIES | SOUTHWEST GAS | Passed | |
| 03/04/2022 | SBEASLE1 | OTHER AGENCIES | PIMA ASSN OF GOVTS | Passed | |
| 03/04/2022 | SBEASLE1 | OTHER AGENCIES | U. S. POST OFFICE | Passed | |
| 03/07/2022 | JOHN BEALL | COT NON-DSD | COMMUNITY PLANNING | Completed | |
| 03/16/2022 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
| 03/17/2022 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: Anything Wood Development Package (1st Review) DP22-0036 TRANSMITTAL DATE: March 17, 2022 DUE DATE: March 21, 2022 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is February 22, 2023 CONTENT REQUIREMENTS 1. COMMENT: 2-06.4.2.D – The page number and the total number of pages in the package (i.e., sheet xx of xx) list on sheet 7-9 are not correct and should reflect the entire DP. 2. COMMENT: 2-06.4.3 – Provide the development package case number, DP22-0036, adjacent to the title block on all sheets. 2-06.4.7 - General Notes The following general notes are required. Additional notes specific to each plan are required where applicable. 2-06.4.7.A - Zoning and Land Use Notes 3. COMMENT: 2-06.4.7.A.3 – Provide the rezoning case number, C9-21-02, in the lower right corner of sheets 7-. 4. COMMENT: 2-06.4.7.A.4 – Remove the reference to Use Specific Standard 4.9.5.D.1 as it is not applicable to the proposed use. 2-06.4.9 - Information on Proposed Development The following information on the proposed project shall be shown on the drawing or added as notes. 5. COMMENT: 2-06.4.9.H.5.a – The vehicle parking space calculation is not correct. Per UDC Article 7.4.3.G Fractional Amounts, when the calculation of required motor vehicle and bicycle parking spaces results in a fractional number, a fraction of one-half or more is adjusted to the next higher whole number. That said the total number required should be 58. 6. COMMENT: 2-06.4.9.Q – Provide the height of the existing building within the foot print> If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov. To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 03/17/2022 | SBEASLE1 | UTILITIES | TUCSON ELECTRIC POWER | Approved | See the document in the "Documents" section of PRO titled: "TEP letter of approval, 03.15.22" |
| 03/21/2022 | SBEASLE1 | COT NON-DSD | PARKS & RECREATION | Approved | Email from: Howard Dutt To: CDRC Mon 3/21/2022 10:29 AM No existing or proposed Tucson Parks and Recreation facilities are affected by this development. Howard Dutt, RLA Project Manager/Landscape Architect Parks and Recreation | City of Tucson Howard.Dutt@tucsonaz.gov main 520.631.2040 |
| 03/23/2022 | JPEELDA1 | COT NON-DSD | FIRE | Approved | |
| 03/24/2022 | DSTIFFE1 | COT NON-DSD | TRAFFIC | Approved | No Comments |
| 04/25/2022 | AWARNER1 | LANDSCAPE | REVIEW | Approved | |
| 04/29/2022 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | Email from: COTDSDPermits To: Steven Shell Fri 4/29/2022 11:28 AM REVIEW NOTICE Returned for Corrections: DP22-0036 DESCRIPTION: Site - Anything Wood. Remodel due to rezoning. 3550 N 1ST AV FEE BALANCE: $ 1,206.50 Please pay at a minimum, the REVIEW category fees. A payment is required before your next submittal. ONLINE PAYMENTS ** If amount doesn't match "Fee Balance", check back in a few hours ** https://www.tucsonaz.gov/pdsd/fees 1- Click on: Pay Planning & Permit Fees 2- Enter Permit Nbr, example: dp20-0000 (not case-sensitive but a hyphen-dash- is needed) 3- Business/Individual Name: Leave this field blank 4- "Continue" 5- In the Pay column - check the boxes 6- "Continue" YOUR NEXT STEPS 1. SEE REVIEW COMMENTS and documents on PRO: www.tucsonaz.gov/pro (If information is not available, check back later after data transfers to PRO.) - Home page, Activity Search, enter the Activity/Permit Number - Permits - click on blue tab - Reviews section - click on REVIEW DETAILS - Documents section - click on VIEW 2. Title your SECOND submittal documents accordingly, example: 2_Comment Response Letter 3. UPLOAD A RESUBMITTAL to Filedrop: - Comment Response Letter (your response to REQUIRES CHANGE comments) - Plan Set (all pages, full set, even if no changes were made) - Any other documents requested by review staff - FILEDROP: https://docs.tucsonaz.gov/Forms/tucsonpermitapp - "Existing Application" - "Permit Number" field: enter the number (and any notes for our staff) - Select "PLANS" for all documents Thank you. Sharon Beasley, Certified Permit Specialist City of Tucson, Planning and Development Services Email: COTDSDpermits@TucsonAz.gov |
| 04/29/2022 | SBEASLE1 | PIMA COUNTY - ADDRESSING | PIMA COUNTY - ADDRESSING | Needs Review |