Permit Number: DP22-0010
Parcel: 132131130

Review Status: Completed

Review Details: DEV PKG - RESUBMITTAL

Permit Number - DP22-0010
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/23/2022 SBEASLE1 START PLANS SUBMITTED Completed
07/11/2022 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
07/14/2022 SBEASLE1 OTHER AGENCIES TUCSON AIRPORT AUTHORITY Approved Approved.
View in the DOCUMENTS section of PRO, titled "Tucson Airport Auth, final letter of approval, 07.13.22"
07/28/2022 AWARNER1 LANDSCAPE REVIEW Approved
08/08/2022 JPEELDA1 FIRE REVIEW Approved
08/12/2022 LOREN MAKUS ENGINEERING REVIEW Approved
08/12/2022 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: CAP Storage @ Tucson Marketplace
Development Package (2nd Review)
DP22-0010

TRANSMITTAL DATE: July 12, 2022

DUE DATE: July 14, 2022

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is January 06, 2023

CONTENT REQUIREMENTS

1. This comment was not fully addressed. Provide the page number and the total number of pages on sheets 20 -24. COMMENT: 2-06.4.2.D – Provide the page number and the total number of pages in the package (i.e., sheet xx of xx) within the title block.

2. This comment was not fully addressed. Provide the case number on sheets 20 -24. COMMENT: 2-06.4.3 – Provide the development package case number, DP22-0010, adjacent to the title block on all sheets.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

3. This comment was not fully addressed. Demonstrate how the requirements of UDC Article 7.4.9.B.1.e, 7.4.9.B.2.a are met. Also, the required 2’ x 6’ space, 7.4.9.B.2.f, is measured from the edge of the bike rack not the center, see UDC Figure 7.4.9-C. COMMENT: 2-06.4.9.H.5.d – Provide a short-term bicycle parking detail that demonstrates how the requirements of UDC Articles 7.4.9.B.1, .2 & 7.4.9.C are met.

Additional comments based on changes made to the plan:
4. COMMENT: 2-06.4.1 – Provide and email address for the Geotechnical Engineer provided on sheet 1.

5. COMMENT: As this DP has not yet been approved remove all revision clouds and deltas from the plan.

If you have any questions about this transmittal, please contact Nicholas Ross at Nicholas.Ross@tucsonaz.gov.

To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
08/15/2022 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change Email from: COTDSDPermits
to: lisa bowers

REVIEW NOTICE

Returned for Corrections: DP22-0010
Site/Grading - CAP Bridges, indoor storage facility.

FEE BALANCE: $ 165.00
ONLINE PAYMENTS
** If the online amount doesn't match "Fee Balance" shown above, check back in a few hours **
https://www.tucsonaz.gov/pdsd/fees
1- Click on: Pay Planning & Permit Fees
2- Enter Permit Nbr, example: dp20-0000
(not case-sensitive but a hyphen-dash- is needed)
3- Business/Individual Name: Leave this field blank
4- "Continue"
5- In the Pay column - check the boxes
6- "Continue"

YOUR NEXT STEPS
1. SEE REVIEW COMMENTS and documents on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, Activity Search, enter the Activity/Permit Number
- Permits - click on blue tab
- Reviews section - click on REVIEW DETAILS
- Documents section - click on VIEW

2. Title your THIRD submittal documents accordingly, example: 3_Comment Response Letter

3. UPLOAD A RESUBMITTAL to Filedrop:
- Comment Response Letter (your response to REQUIRES CHANGE comments)
- Plan Set (all pages, full set, even if no changes were made)
- Any other documents requested by review staff

FILEDROP
https://docs.tucsonaz.gov/Forms/tucsonpermitapp
- "Existing Application"
- "Permit Number" field: enter the number (and any notes for our staff)
- Select "PLANS" for all documents


Sharon Beasley, Certified Permit Technician

City of Tucson, Planning & Development Services Dept.
Email: COTDSDpermits@TucsonAz.gov
(for development packages, land splits, Thursday Presubmittal meetings)
Email: PDSDinquiries@TucsonAz.gov
(for building permits)