Permit Number: DP21-0329
Parcel: 14043011A

Review Status: Completed

Review Details: GRADING

Permit Number - DP21-0329
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/07/2022 AWARNER1 NPPO REVIEW Needs Review CDRC TRANSMITTAL

PROJECT: Martin Reservoir
ACTIVITY NO. DP21-0329
ADDRESS/PARCEL: 990 E VALENCIA RD
ZONING: R-1

7.7. Native Plant Preservation
An approved Native Plant Preservation Plan Sections 7.7.4 is required in accordance with Sections 7.7.3.D.3 & .4 of the Unified Development Code (UDC) and Admin. Manual Section 2-11.0.0 is required prior to Grading Plan approval.

If you have any questions about this transmittal, contact Anne Warner, RLA
PDSD Landscape/NPPO Review at email anne.warner@tucsonaz.gov
01/13/2022 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Martin Reservoir – Rehab & Misc. Improvements
Development Package (1st Review)
DP21-0329

TRANSMITTAL DATE: January 13, 2022

DUE DATE: January 18, 2022

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is December 20, 2022.

2-06.2.0 APPLICATION SUBMITTAL REQUIREMENTS

1. COMMENT: 2-06.2.4 – Remove all references to any building sheets from the plan as they are not part of this review.

2-06.3.0 FORMAT REQUIREMENTS

2. COMMENT: 2-06.3.12 – Revise the Index of Drawing to only include the drawings submitted.

CONTENT REQUIREMENTS

3. COMMENT: 2-06.4.2.D – The page number and the total number of pages in the package (i.e., sheet xx of xx) is not correct as only 3 sheets were submitted.

4. COMMENT: 2-06.4.3 – Provide the development package case number, DP21-0329, adjacent to the title block on all sheets.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

5. COMMENT: 2-06.4.7.A.1 - List as a general note: "Existing zoning is I-1".

6. COMMENT: 2-06.4.7.A.2 - List the gross area of the site/subdivision by square footage and acreage.

7. COMMENT: 2-06.4.7.A.4 - Identify the existing and proposed use of the property as classified per the UDC. List all UDC sections applicable to the proposed uses.

8. COMMENT: 2-06.4.7.A.6.a - Provide a general note on the cover sheet stating “THIS PROJECT IS DESIGNED TO MEET THE OVERLAY ZONE(S) CRITERIA, UDC ARTICLE 5.6 AIRPORT ENVIRONS ZONE (AEZ)”.

If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov.

To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
01/21/2022 SBLOOD1 ENGINEERING REVIEW Approved
01/24/2022 SBEASLE1 ZONING-DECISION LETTER WRITE DECISION LETTER Reqs Change Email from: COTDSDPermits
To: Gabriel Hernandez
Mon 1/24/2022 9:36 AM

REVIEW NOTICE
Returned for Corrections: DP21-0329

DESCRIPTION: Grading - Martin Reservoir. Rehabilitation and miscellaneous improvements. 990 E VALENCIA RD

Fee Balance: $0 (zero) Thank you for the payment.

YOUR NEXT STEPS
1. SEE REVIEW COMMENTS and documents on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, Activity Search, enter the Activity/Permit Number
- Permits - click on blue tab to see different sections
- Reviews section - click on REVIEW DETAILS
- Documents section - click on VIEW

2. UPLOAD A RESUBMITTAL and include:
1) Comment Response Letter (your response to REQUIRES CHANGE comments)
2) Plan Set (all pages, full set, even if no changes were made)
3) Any other documents requested by review staff

Please title your SECOND submittal documents according to this example: 2_Comment Response Letter

FILEDROP for your Resubmittal
https://docs.tucsonaz.gov/Forms/tucsonpermitapp
- Select "Existing Application"
- In the "Permit Number" field, enter the number and, if applicable, any notes for our staff
- Select for documents "PLANS" for quicker downloading of your documents on our end


Thank you.
Sharon Beasley, Building Permit Specialist

City of Tucson, Planning and Development Services
Email: COTDSDpermits@TucsonAz.gov