Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: DP21-0179
Parcel: 13219102B

Review Status: Completed

Review Details: DEV PKG - RESUBMITTAL

Permit Number - DP21-0179
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/01/2021 SBEASLE1 START PLANS SUBMITTED Completed
10/21/2021 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Fry’s Fuel Center #58 – 4733 S Campbell Ave
Development Package (2nd Review)
DP21-0179

TRANSMITTAL DATE: October 21, 2021

DUE DATE: October 28, 2021

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is July 13, 2022.

CONTENT REQUIREMENTS

1. This comment was not addressed. COMMENT: 2-06.4.2.D – The page number and the total number of pages is not correct on sheets L0.1 – L4.1.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

2. This comment was not fully addressed, add the “.1” to the end of the standard. COMMENT: 2-06.4.7.A.4 – Revise General Site Plan Note 3 to include Use Specific Standard, 4.9.9.B.1.

2-06.4.8 - Existing Site Conditions
The following information shall be provided on the plan/plat drawing to indicate the existing conditions on site and within 50 feet of the site. On sites bounded by a street with a width of 50 feet or greater, the existing conditions across the street will be provided.

3. This comment was not fully addressed, provide the recordation information for all easements. COMMENT: 2-06.4.8.B – Based on the Kino Gateway Center final plat recorded under Bk 48, PG 51 there are numerous easements on this parcel. Show the easement on the plan along with the recordation information.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

4. The ratio shown for vehicle parking is not correct and should be 1 space per 300 GFA. COMMENT: 2-06.4.9.H.5.a – Provide a vehicle parking space calculation on the plan. The calculation shall include the number of spaces required (include the ratio used) and the number provided, including the number of spaces required and provided for the physically disabled. If this site is to be considered part of the Fry’s shopping center this calculation shall include the entire center.

5. This comment was not addressed. COMMENT: 2-06.4.9.J – It appears that Campbell Ave is at full ROW width but the curb and sidewalk do not appear to be a future location, see COT MS&R plan found at: https://www.tucsonaz.gov/files/pdsd/plans/MSR.pdf, show the future curb and sidewalk on the plan.

6. This comment was not addressed. COMMENT: 2-06.4.9.L – If the fuel center is not going to be part of the Fry’s shopping center as you are proposing access across the parcel to the south provide a copy of the recorded cross access easement/agreement with your next submittal.

7. As the future curb location was not shown on the plan this comment was not addressed. COMMENT: 2-06.4.9.O – Per UDC Article 6.4.5.C.2 & Table 6.4.5.C-1, ADT of 1,000 or greater, the required street perimeter yard is 21’ as measured to the back of future curb. Show the street perimeter yard setback on the plan correctly.

If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov.

To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
10/26/2021 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
10/29/2021 SBLOOD1 ENGINEERING REVIEW Approved
11/17/2021 AWARNER1 LANDSCAPE REVIEW Approved
11/19/2021 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change Email from: COTDSDPermits
To: Caroline Park, Kevin
Fri 11/19/2021 11:42 AM

Returned for Corrections: DP21-0179

DESCRIPTION: Site/Grading - Fry's Fuel Center #58. 4733 S CAMPBELL Ave.

SEE REVIEW COMMENTS and documents on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, Activity Search, enter the Activity/Permit Number
- Permits - click on blue tab to see different sections
- Reviews section - click on REVIEW DETAILS
- Documents section - click on VIEW

INCLUDE IN RESUBMITTAL
1) Comment Response Letter (your response to REQUIRES CHANGE comments)
2) Plan Set (all pages, full set, even if no changes were made)
3) Any other documents requested by review staff

Please title your THIRD submittal documents according to this example: 3_Comment Response Letter

FILEDROP for your Resubmittal
https://docs.tucsonaz.gov/Forms/tucsonpermitapp
- Select "Existing Application"
- In the "Permit Number" field, enter the number and, if applicable, any notes for our staff


Thank you.
Sharon Beasley, Building Permit Specialist

City of Tucson, Planning and Development Services
Email: COTDSDpermits@TucsonAz.gov
(disregard the email response that will be sent automatically)