Permit Number: DP21-0019
Parcel: 132131210

Review Status: Completed

Review Details: DEV PKG

Permit Number - DP21-0019
Review Name: DEV PKG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/28/2021 SBEASLE1 START PLANS SUBMITTED Completed
01/29/2021 SBEASLE1 UTILITIES TUCSON ELECTRIC POWER Reqs Change (The TEP FACILITIES MAP and TEP REDLINE MAP can be viewed online: www.TucsonAz.gov/Pro. See the Documents section.)

WR#6339933
February 9, 2021

SUBJECT: Salad and Go
DP21-0019

Tucson Electric Power Company (TEP) has reviewed the development plan submitted February 1, 2021. TEP is unable to approve the plan at this time.
There is a TEP pull box and other facilities on site, need to call out each piece of equipment on plans so that we can determine if conflicts exist. See attached facilities map. In order for TEP to approve the plan, our facilities and easements must be depicted on the plans.

Enclosed is a copy of a TEP facility map showing the approximate location of the existing facilities. All costs associated with the relocation of the facilities in conflict will be billable to the developer.

Please resubmit a revised blueline to the City of Tucson for TEP’s review. Should you have any technical questions, please contact the area Designer, Martin Rodriguez, at
(520) 991-5495 should you have any questions.
Sincerely,
Conor Mahoney, Office Support Assistant
Design/Build
01/29/2021 SBEASLE1 OTHER AGENCIES PIMA ASSN OF GOVTS Passed
01/29/2021 SBEASLE1 UTILITIES SOUTHWEST GAS Passed
01/29/2021 SBEASLE1 OTHER AGENCIES U. S. POST OFFICE Passed
02/08/2021 TOM MARTINEZ OTHER AGENCIES AZ DEPT TRANSPORTATION Approved 02/08/21
ADOT South Central District Office and Regional Traffic have reviewed the request and have no comments on this submittal. The development will have no direct impacts to ADOT facilities because of the location. Thank you

Richard La Pierre
Permits Supervisor, South Central District
1221 South Second Avenue
Tucson, Arizona 85713
520.388.4234 (office), 520.307.5893 (cell)
RLaPierre@azdot.gov
02/24/2021 ZELIN CANCHOLA COT NON-DSD TRAFFIC Approved
02/24/2021 STEVE SHIELDS ZONING REVIEW Reqs Change FROM: Development Services Department Zoning Review

PROJECT: Salad and Go at the Bridges
Development Package (1st Review)
DP21-0019

TRANSMITTAL DATE: February 24, 2021

DUE DATE: February 26, 2021

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is January 27, 2022.

CONTENT REQUIREMENTS

1. 2-06.4.3 – Provide the development package case number, DP21-0019, adjacent to the title block on all sheets.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

2. 2-06.4.7.A.4 – Remove the Use Specific Standards from General Note 3 as they are not applicable to a food service use, see PAD-15 Section C.2.3.B.1

3. The Bridges tracking tables to not appear to be complete, contact Elisa Hamblin and request a copy of the Excel File that PDSD feels is the most complete document.

4. Provide a copy of the approved Design Review letter, see PAD-15 Section C.6, with your next submittal,


If you have any questions about this transmittal, please contact Elisa Hamblin, Elisa.Hamblin@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
02/24/2021 SBEASLE1 COT NON-DSD PARKS & RECREATION Approved 02/23/21 No existing or proposed Tucson Parks and Recreation facilities are affected by this development.

Howard B. Dutt, RLA, Landscape Architect
Tucson Parks and Recreation, (520) 837-8040
02/25/2021 SBLOOD1 ENGINEERING REVIEW Reqs Change Sheet 1
1. TSM 8-01.8.0 Please provide calculation that supports the waste stream quantities
2. Add water harvesting hatch to legend.
3. Provide heavier contrast between existing and proposed storm drain manhole in legend.
Sheet 3
1. General Note 18 states 0 long term bicycle parking spaces are required, however the tracking table for Sub-Area "BIII" states this DP requires and provides 2 long term spaces. Please revise accordingly.
Sheet 5
1. Check all ROW dimensions for E Tucson Marketplace BL and S M L King Jr Wy on sheet 5. Dimensions do not add up.
2. Provide SVTs for ingress/egress to S M L King Jr Way between Lot 4 and 5.
3. Please provide striping linework for Keynote 6 callouts within the drive-thru portion separated by the median.
4. Include Keynote 9 where new concrete ramp/sidewalk meets existing sidewalk in the northeast corner.
Sheet 6
1. TSM 8-01.5.2 Provide a 2% min drainage slope away from the dumpster enclosure.
2. Detail 2 Dimension sidewalk/ramp lengths and widths.
3. Add note to plan "connection of new storm drain to proposed storm drain (separate plan) shall not occur until construction is complete/accepted by City".
4. Please note the ground cover as it relates to the water harvesting areas effective volume within the Detention/Retention Summary Keynotes.
5. Detention/Retention Keynote 3 shows a bottom elevation of 92.75, whereas the plan shows spot elevations of 93.00. Please revise accordingly.
6. Please clarify if Storm Drain Note 2 is an option approved by the engineer of work and is therefore not subject to Note 1.
Drainage Statement Comments:
General Comments
1. Please provide onsite watershed map and calculations to demonstrate water harvesting basin function as intended.
2. Please provide 100-year MAX WSEL for Retention Basin and supporting calculations.
3. Please provide calculation(s) demonstrating HGL in new 12" storm drain line utilizing the known HGL at connection as a boundary condition.
Page 1
1. A lot size of 0.61 acres is shown, however the calculation shows 0.72 acres into CB4. Please also note that Per Figure 3, it looks like the flow goes into CB1, not CB4. Please review and revise text and calculation sheet as necessary.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
02/25/2021 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
03/01/2021 SBEASLE1 OTHER AGENCIES TUCSON AIRPORT AUTHORITY Reqs Change February 26, 2021

RE: DP21-0019 / Salad and Go, 1st submittal review, Received January 28, 2021

Thank you for the opportunity to comment on DP21-0019, Salad and Go; 1st Submittal, a development package application for an approximately 0.62 acre site, located southwest of the intersection of East Tucson Marketplace Boulevard and South Kino Parkway. The property is zoned Planned Area Development 15 (PAD-15), with the proposed use being food service excluding soup kitchens.

This site is within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace.

The Tucson Airport Authority previously commented on the Major Change to PAD-15, comment letter is dated March 9th, 2018, with this comment letter being adopted on Page B7-B8 of City of Tucson Ordinance 11552. This proposed project area is contained within the areas identified by this City of Tucson Ordinance.

The Tucson Airport Authority conditionally approves the subject request contingent upon the following conditions of approval, as noted below. These conditions shall be identified in the general notes of the revised development plan. Please note that Condition #2 does not need to be included on the revised development package if the property owner has already recorded the Avigation Easement over all of PAD Sub-Area B-III and the Tucson Airport Authority has confirmed receiving a copy of this recorded Avigation Easement.

Conditions of approval:

1. "According to the Federal Aviation Administration (FAA) Notice Criteria Tool, this project area is located in proximity to a navigation facility and could impact navigation signal reception. As this project site develops, all applicants shall file FAA Form 7460 with the FAA at least 45 days before construction activities begin unless FAA staff, with the Obstruction Evaluation / Airport Airspace Analysis (OE/AAA), provides the project applicant with written communication that filing FAA Form 7460 is not required. It is highly recommended that the applicant file earlier than 45 days to provide the applicant with sufficient time to respond to any concerns which are identified by the FAA. Any cranes which are used must also be identified with Form 7460. Please file Form 7460 at https://oeaaa.faa.gov/oeaaa/external/portal.jsp"

2. "That prior to the City's approval of this development package, the property owner shall record the Avigation Easement for all of PAD Sub-Area B-III, which discloses the existence, and operational characteristics of the Tucson International Airport to future owners or tenants of the property and further conveys the right to the public to lawfully use the airspace above the property. The Avigation Easement shall be recorded in a manner with the Pima County recorder which shall document it as having title liability. The content of such documents shall be according to the form and instructions provided.

The current property owner or person authorized to sign on behalf of the current property owner shall complete, sign, and record the Avigation Easement. Please record the Avigation Easement with the Pima County Recorder's Office. Once the Avigation Easement is recorded please send a complete copy of the recorded easement document to Tucson Airport Authority by either email (send to srobidoux@flytucson.com) or to the mailing address provided below.
Scott Robidoux
Senior Airport Planner
Tucson Airport Authority
7250 South Tucson Boulevard
Suite 300
Tucson, AZ 85756"

Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811.

Respectfully,
Scott Robidoux, C.M., Senior Airport Planner
03/01/2021 ANDREW CONNOR LANDSCAPE REVIEW Reqs Change ADMINISTRATIVE MANUAL

Identification and Descriptive Data

The Development Package will may be needed and should contain the following identification in the lower right corner of each sheet:

Any other relevant case number for reviews or modifications that affect the site.

Add case number DP21-0019 on each sheet.

Provide a copy of the Design Review letter PAD-15 Section C.6

Ensure that Zoning, Engineering comments and concerns are addressed prior to landscape section approval.
03/02/2021 MROSS2 COT NON-DSD FIRE Approved
03/12/2021 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change DATE: March 12, 2021
Returned for Corrections

PERMIT/ACTIVITY: DP21-0019
DESCRIPTION: SITE - Salad and Go at The Bridges, new restaurant.

FEE BALANCE: $0 (zero) Thank you for the payment.

RESUBMITTAL
Submit the following documents to:
https://docs.tucsonaz.gov/Forms/tucsonpermitapp
(Select "Existing Application", then the permit number)
1) Comment Response Letter
(your response to the reviewer's Requires Change comments)
2) Plan Set (all pages, full set, even if no changes were made)
3) Any other documents requested by review staff

- Title the documents for your 2nd submittal starting with the
submittal number, for example: 2_Plan_Set

SEE REVIEW COMMENTS and your submitted documents on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, Activity Search, enter the Activity/Permit Number
- Permits - click on blue tab
- Reviews - click on Review Details
- Documents - click on View to the right of each document

For all NEW development package submittals on the Filedrop page, select the box: "SITE REVIEW...".

Thank you.

City of Tucson
Attn: Sharon Beasley, Permit Specialist
Planning and Development Services
email: COTDSDPermits@TucsonAz.gov
03/12/2021 JOHN BEALL COT NON-DSD COMMUNITY PLANNING Passed