Permit Review Detail
Review Status: Completed
Review Details: DEV PKG - OK TO SUBMIT
Permit Number - DP20-0208
Review Name: DEV PKG - OK TO SUBMIT
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/04/2021 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 11/08/2021 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: Desert Metals Development Package (Revision #1 OK to Submit) DP20-0208 TRANSMITTAL DATE: November 8, 2021 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). 2-06.4.9 - Information on Proposed Development The following information on the proposed project shall be shown on the drawing or added as notes. 1. COMMENT: 2-06.4.9.R – Per TSM Section 7-01.4.1.A at least one sidewalk is required to a project from each street on which the project has frontage. The proposed asphalt pedestrian path does not meet the requirements of TSM Section 7-01.4.3.C. If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov. To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 11/15/2021 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | Provide a pedestrian surface that complies with TSM 7-014.3.C Loren Makus lwmakus@tucsonaz.gov |
| 11/19/2021 | SBEASLE1 | ZONING-DECISION LETTER | WRITE DECISION LETTER | Passed |