Permit Review Detail
Review Status: Completed
Review Details: REVISION - - 1ST
Permit Number - DP20-0205
Review Name: REVISION - - 1ST
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/04/2021 | SBEASLE1 | ENGINEERING | REVIEW | Approved | Approved by Loren Makus on 04/22/21 during the OK to Submit. |
05/06/2021 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
05/17/2021 | JPEELDA1 | COT NON-DSD | FIRE | Approved | |
05/28/2021 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
05/28/2021 | SSHIELD1 | LANDSCAPE | REVIEW | Approved | |
06/09/2021 | AWARNER1 | DESIGN PROFESSIONAL | REVIEW | Reqs Change | 6/16/21 Review for compliance with RNA-DRB-20-07 / HPZ-20-073 (/T20SA00320). By Maria Gayosso 1. As requested during the previous review, the following note must be added to Page C1.0 the Development Package: "Archeological monitoring required during construction in appropriate locations as determined by the City of Tucson Historic Preservation Officer". 2. On Sheet L5.0 and L5.2, please include the following note: "No artificial turf to be installed". |
06/15/2021 | FRANK PODGORSKI | HPZ ADVISORY BOARD | HPZ ADVISORY BOARD DATE | Reqs Change | The proposed project was reviewed by the Plans Review Subcommittee with 3 conditions in the Decision Notice 1) Improvements do not include artificial turf; 2) Archaeological monitoring of appropriate locations during construction, as required by the CHPO; and 3) Relocation of interpretative signage to preserve lines of sight to Sentinel Peak. There are no indications of artificial turf within the landscape plans; however, there are notes about artificial turf in the details which appears to be an oversight. There are no notes about archaeological monitoring included in the plans. The plans should be revised to include this note and that the CHPO will be consulted prior to the start of construction. Relocation of interpretative signage appears to be addressed correctly. |
06/17/2021 | JOE LINVILLE | COT NON-DSD | LANDSCAPE | Approved | |
06/28/2021 | SBEASLE1 | ZONING-DECISION LETTER | WRITE DECISION LETTER | Reqs Change | Email from: COTDSDPermits To: Jason Morse Mon 6/28/2021 10:27 AM REVISION Returned for Corrections Notice PERMIT/ACTIVITY: DP20-0205 DESCRIPTION: Site/Grading/SWPPP - Tucson Convention Center improvements. Meeting rooms, parking garage, site improvements. 260 S CHURCH AV FEES: deferred until further notice INCLUDE IN YOUR RESUBMITTAL 1) Comment Response Letter (your response to the reviewer's Requires Change comments) 2) Plan Set or sheets 3) Any other documents requested by review staff Please title your 2nd submittal revision documents according to this example: REV-1_2_Comment Response Letter, 01.01.21 FILEDROP https://docs.tucsonaz.gov/Forms/tucsonpermitapp (Select "Existing Application", then enter the permit number) SEE REVIEW COMMENTS and documents on PRO: www.tucsonaz.gov/pro (If information is not available, check back later after data transfers to PRO.) - Home page, Activity Search, enter the Activity/Permit Number - Permits - click on blue tab and you will see different sections - Reviews section - click on REVIEW DETAILS - Documents section - click on VIEW Thank you. Sharon Beasley, Permit Specialist City of Tucson, Planning and Development Services Email for Development Pkgs: COTDSDpermits@TucsonAz.gov (disregard the email response that will be sent automatically) Email for Building Permits: PDSDinquiries@TucsonAz.gov HOLIDAY: All City of Tucson offices (except for emergency services) will be closed on Monday, July 5th, for the July 4th holiday. |
06/28/2021 | SBEASLE1 | COT NON-DSD | TRAFFIC | Needs Review | |
08/17/2021 | SBEASLE1 | UTILITIES | TUCSON ELECTRIC POWER | Approved | Email from: Geerligs, Diane <DGeerligs@tep.com> To: CDRC Tue 8/17/2021 4:51 PM Tucson Electric Power Co. (TEP) has reviewed and has no objection to the Tucson Convention Ctr, DP20-0205, submitted on June 18th, 2021. Please call the New Construction Department at 520-918-8300 to apply for service. Submit a final set of approved plans including electrical load and offsite improvement plans to determine how TEP will serve this development. If easements are required, they will be obtained by separate instrument. Removal or relocation of existing TEP facilities will be at the Developer’s expense. Tucson Electric Power Co. Land Resources Department |