Permit Review Detail
Review Status: Completed
Review Details: DEV PKG
Permit Number - DP20-0204
Review Name: DEV PKG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/05/2021 | GDAURIA1 | COT NON-DSD | FIRE | Reqs Change | * Show a hydrant within 100' of the future FDC. |
10/12/2020 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
10/12/2020 | SBEASLE1 | UTILITIES | TUCSON ELECTRIC POWER | Passed | approval letter for Rudy’s, DP20-0204. Thank you, Conor Mahoney Design Administrator OH201 Desk: (520) 918-8388 Cell: (520) 404-8437 |
10/12/2020 | SBEASLE1 | OTHER AGENCIES | PIMA ASSN OF GOVTS | Passed | |
10/12/2020 | SBEASLE1 | UTILITIES | SOUTHWEST GAS | Passed | |
10/12/2020 | SBEASLE1 | OTHER AGENCIES | U. S. POST OFFICE | Passed | |
11/06/2020 | ANDREW CONNOR | LANDSCAPE | REVIEW | Reqs Change | ADMINISTRATIVE MANUAL 4.1 Identification and Descriptive Data All improvements and site information, such as adjacent rights-of-way and property lines, shown on the landscape plan will be identical in size and location to those shown on the base plan (site plan or tentative plat). Should amendments be required to the base plan through the review process, the same amendments will be made to the landscape plan which will then be resubmitted along with the base plan. The Development Package will contain the following identification in the lower right corner of each sheet: Any relevant case numbers for reviews or modifications that affect the site. Provide Case # DP20-0204 on each sheet. Indicate graphically, where possible, compliance with conditions Rezoning C9-20-07 Landscape section cannot approve the development package until Rezoning process is completed. Ensure that Zoning and Engineering comments are addressed prior to landscape section approval. Additional comments may apply |
11/09/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
11/09/2020 | ZELIN CANCHOLA | COT NON-DSD | TRAFFIC | Approved | |
11/10/2020 | SBEASLE1 | OTHER AGENCIES | TUCSON AIRPORT AUTHORITY | Approved | November 9, 2020 RE: DP20-0204 / Site/Grading/SWPPP - Rudy's at Ajo and I-10. New restaurant / 1st Submittal, Received October 12, 2020 Thank you for the opportunity to comment on DP20-0204, Rudy's at Ajo and I-10; 1st Submittal, a development package application for an approximately 1.58 acre site, located southeast of the intersection of East Ajo Way and Kino Parkway. The property is zoned Commercial Zone (C-2), with the proposed development to construct a new restaurant. This site is within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace. The Tucson Airport Authority previously commented on the rezoning case (C9-20-07 and comment letter dated June 29, 2020) where this project is proposed to be occurring. The Tucson Airport Authority recognizes that the rezoning conditions that were provided in the comment letter for the rezoning case are identified as Condition 10 in the plan set for this project. As a friendly reminder, the Tucson Airport Authority requests the applicant to provide a copy of the recorded Avigation Easement for the entire property associated with rezoning case C9-20-07 and to make sure to satisfy the condition for FAA Form 7460 as part of this project. The Tucson Airport Authority approves the proposed project. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811. Respectfully, Scott Robidoux, C.M., Senior Airport Planner Tucson Airport Authority |
11/10/2020 | SBEASLE1 | COT NON-DSD | PARKS & RECREATION | Approved | No existing or proposed Tucson Parks and Recreation facilities are affected by this development. Howard B. Dutt, RLA Landscape Architect Tucson Parks and Recreation (520) 837-8040 |
11/12/2020 | JOHN BEALL | COT NON-DSD | COMMUNITY PLANNING | Approved | |
11/13/2020 | TOM MARTINEZ | OTHER AGENCIES | AZ DEPT TRANSPORTATION | Approved | ADOT South Central District has no comments and/or concerns for this project; due to the development location. It will pose no direct impact upon the state system. Richard La Pierre Permits Supervisor, South Central District 1221 South Second Avenue, Tucson, Arizona 85713 520.388.4234 (office), 520.307.5893 (cell) RLaPierre@azdot.gov |
11/23/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Section Manager PROJECT: Rudy’s at Ajo & I-10 Development Package (1st Review) DP20-0204 TRANSMITTAL DATE: November 23, 2020 DUE DATE: November 09, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is October 11, 2021. 2-06.4.7.A - Zoning and Land Use Notes 1. COMMENT: 2-06.4.7.A.6.a - COMMENT: Provide a general note on the cover sheet stating “THIS PROJECT IS DESIGNED TO MEET THE OVERLAY ZONE(S) CRITERIA, UDC ARTICLE 5.4 MAJOR STREETS AND ROUTES SETBACK ZONE (MS&R).” 2-06.4.9 - Information on Proposed Development The following information on the proposed project shall be shown on the drawing or added as notes. 2. COMMENT: 2-06.4.9.H.5.d – Detail “H” sheet 6 short-term bicycle parking detail does not reflect the same area of the site that is called out under Keynote 20, Also this detail shows the 2’x4’ required space for the bike encroaching into the vehicle parking space. 3. COMMENT: 2-06.4.9.R – Demonstrate how the requirements of TSM 7-01.4.1.A are met. 4. COMMENT: Until DP20-0189 is approved Zoning cannot approved this DP. If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
12/10/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | DP20-0204 1. Provide bollards along the side walls of the solid waste container enclosures. TS 8-01.9 2. Provide dimensions for the enclosure to show the truck access gates meet the technical standards. TS 8-01.9 3. Make sure the grading limits on the various sheets are consistent. 4. Clearly identify the grading/development limits for this phase of the development. 5. Clearly identify the building downspout. On sheet 3 the apparent downspout is given the keynote for a fence or wall. |
12/11/2020 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | DATE: December 11, 2020 RETURNED FOR CORRECTIONS NOTICE Your Next Steps: Resubmittal of updated/corrected documents IMPORTANT - NEW FILEDROP: https://docs.tucsonaz.gov/Forms/tucsonpermitapp Select "Existing Application" FYI - For all NEW submittals (not this resubmittal) on the new Filedrop page, select the box: "SITE REVIEW..." so it is routed to correct staff member for quicker processing. PERMIT/ACTIVITY: DP20-0204 DESCRIPTION: Site/Grading/SWPPP - Rudy's at Ajo and I-10. New restaurant. FEE BALANCE: $0 (zero) Thank you for the payment. SEE REVIEW COMMENTS and your submitted documents on PRO: www.tucsonaz.gov/pro (If information is not available, check back later after data transfers to PRO.) - Home page, Activity Search, enter the Activity/Permit Number - Permits - click on blue tab - Reviews - click on Review Details - Documents - click on View to the right of each document RESUBMITTAL OF UPDATED/CORRECTED DOCUMENTS Submit documents to NEW FILEDROP: https://docs.tucsonaz.gov/Forms/tucsonpermitapp 1) Comment Response Letter (your response to the reviewer's Requires Change comments) 2) Plan Set (all pages, full set, even if no changes were made) 3) Any other documents requested by review staff - Title the documents for your 2nd submittal starting with the submittal number, for example: 2_Plan_Set Thank you. City of Tucson Attn: Sharon Beasley, Permit Specialist Planning and Development Services email: COTDSDPermits@TucsonAz.gov |