| 09/28/2020 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 10/01/2020 | GDAURIA1 | FIRE | REVIEW | Completed | |
| 10/26/2020 | ANDREW CONNOR | LANDSCAPE | REVIEW | Reqs Change | ADMINISTRATIVE MANUAL 4.1 Identification and Descriptive Data All improvements and site information, such as adjacent rights-of-way and property lines, shown on the landscape plan will be identical in size and location to those shown on the base plan (site plan or tentative plat). Should amendments be required to the base plan through the review process, the same amendments will be made to the landscape plan which will then be resubmitted along with the base plan. The Development Package will contain the following identification in the lower right corner of each sheet: Any relevant case numbers for reviews or modifications that affect the site. Provide Case # DP20-0190 on each sheet. Ensure that Zoning and Engineering comments are addressed prior to landscape section approval. Additional comments may apply |
| 10/26/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Section Manager PROJECT: Manitoba Development – Retention/Detention Basin Development Package (1st Review) DP20-0190 TRANSMITTAL DATE: October 26, 2020 DUE DATE: October 26, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is September 27, 2021. 1. 2-06.4.3 – Provide the development package case number, DP20-0190 and the following case numbers to the plan S15-018, DS14-12 & DP13-0231, adjacent to the title block on all sheets. 2-06.5.0 FLEXIBLE LOT DEVELOPMENT (FLD - ADDITIONAL REQUIREMENTS) 2-06.5.3 Additional Information The following are required in addition to the requirements of the tentative plat or site plan, whichever is applicable: 2. 2-06.5.3.C – Clearly demonstrate how this basin area can function as Functional Open Space as approved on DP13-0231> If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 11/24/2020 | SBLOOD1 | ENGINEERING | REVIEW | Reqs Change | 1. Please provide substantiation for everything in the drainage report and on the plans. I see on the plans and in the report a 3.1 cfs entering the detention/retention basin, and I see the hydrologic reports, but without any of the drainage areas or delineations mapped out. Providing the original drainage report for DP13-0231 referenced in the new report would be helpful. Stephen Blood stephen.blood@tucsonaz.gov |
| 11/25/2020 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | DATE: November 25, 2020 RETURNED FOR CORRECTIONS NOTICE Your Next Steps: Resubmittal of updated/corrected documents IMPORTANT: On the upload page, select the box: "Site Review..." when sending your next submittal. NEW FILEDROP: https://docs.tucsonaz.gov/Forms/tucsonpermitapp PERMIT/ACTIVITY: DP20-0190 DESCRIPTION: GRADING/FLOODPLAIN - Manitoba Development. Modify detention basin. (Revision to DP13-0231). FEE BALANCE: $0 (zero) Thank you for the payment. SEE REVIEW COMMENTS and your submitted documents on PRO: www.tucsonaz.gov/pro (If information is not available, check back later after data transfers to PRO.) - Home page, Activity Search, enter the Activity/Permit Number - Permits - click on blue tab - Reviews - click on Review Details - Documents - click on View to the right of each document YOUR NEXT STEP: Submit documents (NEW LINK for all uploads): https://docs.tucsonaz.gov/Forms/tucsonpermitapp 1) Comment Response Letter (your response to the reviewer's Requires Change comments) 2) Plan Set (all pages, full set, even if no changes were made) 3) Any other documents requested by review staff - Title the documents for your 2nd submittal starting with the submittal number, for example: 2_Plan_Set IMPORTANT: On the upload page, select the box: "Site Review..." when sending your next submittal. City of Tucson Attn: Sharon Beasley, Permit Specialist Planning and Development Services email: COTDSDPermits@TucsonAz.gov |