Review Details: DEV PKG - OK TO SUBMIT
Permit Number - DP19-0302
Review Name: DEV PKG - OK TO SUBMIT
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/11/2019 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 12/11/2019 | SBEASLE1 | PIMA COUNTY - ADDRESSING | PIMA COUNTY - ADDRESSING | Passed | |
| 12/11/2019 | SBEASLE1 | WWM | REVIEW | Passed | |
| 12/12/2019 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Section Manager PROJECT: Lakes Apartments Solar Canopies Development Package (1st Review) DP19-0302 TRANSMITTAL DATE: December 12, 2019 DUE DATE: OK to Submti COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is December 11, 2020. 2-06.3.0 FORMAT REQUIREMENTS 1. 2-06.3.2 - All mapped data shall be drawn at an engineering scale having no more than 50 feet to the inch. 2. 2-06.3.12 - Remove sheet 3 from the plan set as it is not relevant. Revise the drawing index to only include the development package sheets. CONTENT REQUIREMENTS 3. 2-06.4.2.D - Revise the sheet numbers as sheet 3 is to be removed. 4. 2-06.4.3 - Provide the development package case number, DP19-0302 , adjacent to the title block on all sheets. 5. 2-06.4.4 - The project-location map shall cover approximately one square mile and be drawn at a minimum scale of three inch equals one 6. 2-06.4.2.C - Provide the section, township, and range and label the section corners on the location map. 2-06.4.7 - General Notes The following general notes are required. Additional notes specific to each plan are required where applicable. 7. 2-06.4.7.A - Zoning and Land Use Notes 8. 2-06.4.7.A.1 - List as a general note: "Existing zoning is O-3. 9. 2-06.4.7.A.2 - List the gross area of the site/subdivision by square footage and acreage. 10. 2-06.4.7.A.4 - Identify the existing and proposed use of the property as classified per the UDC. List all UDC sections applicable to the proposed uses. 2-06.4.9 - Information on Proposed Development The following information on the proposed project shall be shown on the drawing or added as notes. 11. 2-06.4.9.F - All existing zoning classifications on and adjacent to the project (including across any adjacent right-of-way) shall be indicated on the drawing with zoning boundaries clearly defined. 12. 2-06.4.9.H.5 - Per UDC Article 7.4.6.F.2.a.(1) show the required 1' setback to the PAAL on the plans. 13. 2-06.4.9.O - Provide a setback dimension from the proposed canopies shown along the east property line. Per UDC Table 6.3-3.A the minimum setback is 10'-0". 14. Remove all building code references from the development package plans. If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 12/13/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | DP19-0302 1) Show on plans the boundary for the FEMA Zone AH 100 year floodplain which crosses the northeast corner of the site and appears to impact canopy #1. Please note that a floodplain use permit will be needed for the building plans associated with canopy #1 |
| 12/16/2019 | SBEASLE1 | ZONING-DECISION LETTER | WRITE DECISION LETTER | Passed |