Permit Number: DP19-0205
Parcel: 117090260

Address:
1021 S 6TH AV

Review Status: Completed

Review Details: DEV PKG - RESUBMITTAL

Permit Number - DP19-0205
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/07/2020 MRESS1 DDO Prep DRB HEARING DATE Approved
01/16/2020 DAVID RIVERA ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: David Rivera
PDSD Zoning Review Section

PROJECT: DP for Mattress Factory / Shopping Center development (Retail)
Development Package (2nd Review) 1021 S. 6th Avenue
DP19-0205 - C-3 Zoning

TRANSMITTAL DATE: January 15, 2020
DUE DATE: January 21, 2020

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is August 22, 2020.

SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)

***Address remaining comments 1 and 2 and resubmit DP plans for review. (Previous comments noted below are for reference.)

1. Comment: Previous Comment 7 is still applicable until the PC Tax Parcel Combo Documents are submitted to PDSD.

2. COMMENT: For Previous Comments 7,9,15, and 16, provide the email correspondence from TDOT that 6th Avenue is at its maximum width and that future R/W will not be required. (While this location is very close to the south edge of the Downtown Insert it is to close to the edge and could be interpreted as outside the insert area.)


PREVIOUS COMMENT 7: 2-06.4.8.A - This site is made up of three parcels. Prior to approval of the DP a Pima County Tax Parcel Combo will be required.


PREVIOUS COMMENT 9: 2-06.4.9.H.2 -
Also, Sixth Avenue is a major street and per the adopted MS&R map, will be widened to 90 feet. Per your plan the ½ R/W is just short of 40 feet in width. The future right of way information shall be drawn, labeled and dimensioned, including the future svt's.


PREVIOUSCOMMENT 15: 2-06.4.9.I - If right of way dedication is required revise the drawing with the new right of way line, future curb and sidewalks, labeled and dimensioned.


PREVIOUS COMMENT 16: 2-06.4.9.J - If dedication is not required or proposed draw the Major Street right-of-way lines for Sixth Avenue, (Add the MS&R future sidewalk, right-of-way lines, sight visibility triangles, etc.).


PREVIOUS COMMENT 17: 2-06.4.9.O - Sixth Avenue is an Arterial roadway listed on the MS&R map. The street building setbacks along the Sixth Avenue frontage should be labeled from the existing and future back of curb locations.


***For additional information on the any standard presented in this memo, please refer to the City of Tucson "Unified Development Code" - Administrative Manual Section 2-06 or Technical Standards noted in the comments. https://www.tucsonaz.gov/pdsd/all-codes-plans-determinations


If you have any questions about this transmittal, Contact David Rivera at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields any time during the week at (520) 837-4956 or email Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
01/17/2020 ANDREW CONNOR LANDSCAPE REVIEW Approved
01/21/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
01/21/2020 DAVID RIVERA ZONING HC REVIEW Approved
01/27/2020 MARTIN BROWN COT NON-DSD FIRE Approved
01/27/2020 JOHN VAN WINKLE ENGINEERING REVIEW Approved
01/28/2020 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change PLAN RETURNED FOR CORRECTIONS NOTICE
A resubmittal with a Comment Response Letter is required.

DESCRIPTION: SITE/GRADING - Mattress Factory, building expansion.

PERMIT: DP19-0205
Please include this number on all future correspondence and in Filedrop's "Project Description" field.

FEE BALANCE: $0 (zero)
VIEW DOCUMENTS and reviewer's comments on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, left side, Activity Search, enter the Activity Number
- Permits section, click on blue tab
- Documents section, click on blue icon to the right of each document
- Reviews section, click on Review Details

YOUR NEXT STEPS: Submit the following items to the Filedrop - https://www.tucsonaz.gov/file-upload-pdsd
1) Comment Response Letter (your response to the reviewer's Requires Change comments)
2) Plan Set (all pages, full set)
3) Any other documents requested by review staff

- In the Project Description field, enter the Activity/Permit Number
- Name your 3rd submittal documents to start with the number, for example: 3_Plan_Set

Thank you.
Sharon Beasley, Permit Specialist

City of Tucson
Planning and Development Services
Attn: Permit Counter/Payments
201 N. Stone Avenue, 2nd Floor
Tucson, AZ 85701
email: COTDSDPermits@TucsonAz.gov
12/20/2019 SBEASLE1 START PLANS SUBMITTED Completed

Final Status

Task End Date Reviewer's Name Type of Review Description
01/28/2020 SBEASLE1 OUT TO CUSTOMER Completed