Permit Number: DP19-0152
Parcel: 117170020

Review Status: Completed

Review Details: DEV PKG - RESUBMITTAL

Permit Number - DP19-0152
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/20/2019 SBEASLE1 START PLANS SUBMITTED Completed
09/25/2019 PAUL CAMARENA ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Paul Camarena
PDSD Zoning Review Section

PROJECT: Lewis Hotel Lofts - Multi-use development / Multi-family and Retail
Development Package (2nd Review) - Related MDR-13-01/T13SA00082
DP19-0152 - OCR-2 Zoning / 140 E. Broadway Boulevard

TRANSMITTAL DATE: September 25, 2019
DUE DATE: October 16, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is June 17, 2020.

SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)


2-06.3.0 FORMAT REQUIREMENTS


2-06.4.7.A.6.a - List additional applications and overlays, by case number (if applicable), in lower right corner of each sheet. As a general note provide the type of application processed or overlays applicable, a statement that the project meets the criteria/conditions of the additional application or overlay, the case number, date of approval, what was approved, and the conditions of approval, if any.

The comment below is still applicable add the information for the condition of approval.

5. COMMENT: If applicable add the information as noted by the standard above.




2-06.4.8.B - All easements shall be drawn on the plan. The recordation information, location, width, and purpose of all easements on site will be stated. Blanket easements should be listed in the notes, together with recordation data and their proposed status. Should an easement not be in use and be proposed for vacation or have been abandoned, so indicate. However, should the easement be in conflict with any proposed building location, vacation of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided.

The comment below is still applicable: Provide the use agreement documents on the next submittal

9. COMMENT: If there is no intent to combine the two parcels, a cross access agreement or easement may or will be required.





***For additional information on the any standard presented in this memo, please refer to the City of Tucson "Unified Development Code" - Administrative Manual Section 2-06 or Technical Standards noted in the comments. https://www.tucsonaz.gov/pdsd/all-codes-plans-determinations


If you have any questions about this transmittal, Contact Paul Camarena at (520) 837-4082 or by email Paul.Camarena@tucsonaz.gov or contact Steve Shields at (520) 837-4956 or email Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
09/25/2019 PCAMARE1 ZONING HC REVIEW Passed
10/15/2019 ANDREW CONNOR LANDSCAPE REVIEW Reqs Change The Development Package will contain the following identification in the lower right corner of each sheet:

Compliance with any conditions of the IID review and approval.

Ensure that all Zoning, Engineering, and Design Professional comments and concerns are addressed.

Additional comments may apply.
10/18/2019 NROSS1 DESIGN PROFESSIONAL REVIEW Reqs Change Applicant has completed IID process but needs Directors Decision Letter prior to approval
10/18/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change A note stating that the residential units (2nd story and above) will not discharge through the backwater valve was not found on the utility sheet. Note that any plumbing fixture located on a floor more than 12" above the next upstream manhole rim may not discharge through a backwater valve (i.e. fixtures located on floors higher than 96.94'). [Initial comment: The rim elevation of the next upstream sanitary manhole (2395.94') is less than 12" below the first floor elevations (2396.35', 2396.50', and 2396.80'). Provide a note on the plans requiring the installation of a backwater valve when future plumbing activities take place. Note also that floors discharging from above 2396.94' shall not discharge through the backwater valve. Reference: Section 714.1, IPC 2018, as amended by the City of Tucson.]
10/23/2019 JOHN VAN WINKLE ENGINEERING REVIEW Approved
10/24/2019 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change PLAN RETURNED FOR CORRECTIONS NOTICE
- A resubmittal is required
Permit/Activity Number: DP19-0152
Project Description: SITE / Grading / IID - Lewis Hotel Lofts, 5-story residential and commercial.
Project Manager: Alexandra.Hines@TucsonAz.gov, (520) 837-6975

The fee balance is $0 (zero). Thank you for the payment.
To view the review comments: www.tucsonaz.gov/PRO, enter the Permit/Activity Number.
(If information isn't shown yet, check back later as data uploads to PRO periodically.)
Submit the following items to the PDSD Filedrop: https://www.tucsonaz.gov/file-upload-pdsd.
In the Project Description field, please include the Activity Number.
1) Comment Response Letter (your response to the reviewer's “Requires changes” comments)
2) Plan Set (all pages, full set)
3) Any other documents requested by review staff
4) Name your 3rd submittal documents accordingly, for example: 3_Plan_Set

Thank you.
Sharon Beasley, Permit Specialist

City of Tucson
Planning and Development Services
Attn: Permit Counter/Payments
201 N. Stone Avenue, First Floor
Tucson, AZ 85701

Final Status

Task End Date Reviewer's Name Type of Review Description
10/24/2019 SBEASLE1 OUT TO CUSTOMER Completed