Permit Review Detail
Review Status: Completed
Review Details: DEV PKG
Permit Number - DP19-0134
Review Name: DEV PKG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/03/2019 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 06/04/2019 | MARTIN BROWN | COT NON-DSD | FIRE | Reqs Change | The sprinkler system inside the building must be extended to cover new canopy. Please indicate on plans the sprinklers will be a deferred submittal. Indicate a fire department approved lock box will be be installed on the proposed gate. Please locate existing and/or proposed fire hydrant(s), with dimensions to property line. |
| 06/06/2019 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Section Manager PROJECT: Tucson Rolling Shutters - Canopy Addtion Development Package (1st Review) DP19-0134 TRANSMITTAL DATE: June 6, 2019 DUE DATE: July 01, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is June 01, 2020. 2-06.3.0 FORMAT REQUIREMENTS 1. 2-06.3.5 - A three-inch by five-inch space shall be reserved in the lower right quadrant of each sheet for an approval stamp 2. 2-06.3.7 - Move the project-location map to the upper right corner of the cover sheet. CONTENT REQUIREMENTS 3. 2-06.4.1 - The name, mailing and email addresses, and phone number of the primary property owner of the site, the developer of the project, registrant(s), and other person(s), firm(s), or organization(s) that prepared the development package documents shall be provided on the right half of the cover sheet. 4. 2-06.4.2.D - Provide the page number and the total number of pages in the package (i.e., sheet xx of xx). 5. 2-06.4.3 - Provide the development package case number, DP19-0134 , adjacent to the title block on all sheets. 6. 2-06.4.4 - The project-location map shall cover approximately one square mile and be drawn at a minimum scale of three inch equals one mile 7. 2-06.4.2.C - Label the section, township, and range; section corners; north arrow; and the scale on the location map. 2-06.4.7 - General Notes The following general notes are required. Additional notes specific to each plan are required where applicable. 2-06.4.7.A - Zoning and Land Use Notes 8. 2-06.4.7.A.4 - Identify the existing and proposed use of the property as classified per the UDC. List all UDC sections applicable to the proposed uses. This use should be listed as General Manufacturing subject to Use Specific Standards 4.9.5.C.2, .4, .5, .6, & .8 and 4.9.13.Q. 9. 2-06.4.7.A.6.a - Provide a general note on the cover sheet stating "THIS PROJECT IS DESIGNED TO MEET THE OVERLAY ZONE(S) CRITERIA, UDC ARTICLE 5.6 AIRPORT ENVIRONS ZONE (AEZ)." 2-06.4.8 - Existing Site Conditions The following information shall be provided on the plan/plat drawing to indicate the existing conditions on site and within 50 feet of the site. On sites bounded by a street with a width of 50 feet or greater, the existing conditions across the street will be provided. 10. 2-06.4.8.C - The following information regarding existing private or public right-of-way adjacent to or within the site shall be provided: the name, right-of-way width, recordation data, type and dimensioned width of paving, curbs, curb cuts, and sidewalks. 11. Remove the last approved site plan from this Development Package as it is for reference only. If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 06/06/2019 | SSHIELD1 | LANDSCAPE | REVIEW | Passed | |
| 06/06/2019 | SSHIELD1 | ZONING HC | REVIEW | Passed | |
| 06/06/2019 | SSHIELD1 | PLUMBING-COMMERCIAL | REVIEW | Passed | |
| 06/06/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
| 06/07/2019 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | PLAN RETURNED FOR CORRECTIONS NOTICE The reviews have been completed and a resubmittal is required. Fee Balance: $577.50 Prior to the completion of the next review, we require payment of the total fees (or the Review fees at a minimum). You may pay in person at the City of Tucson permit counter or mail a check payable to the City of Tucson (see address below). Please write your Activity Number on the check stub. Activity Number: DP19-0134 Project Description: SITE - Tucson Rolling Shutters, canopy addition to existing building. For review comments, visit PRO at www.tucsonaz.gov/PRO, then search by Activity Number. (If information isn't shown yet, check back later as data flows to PRO periodically throughout the day.) After all corrections are made, please name your 2nd submittal documents accordingly, for example: 2_Plan_Set. Submit the following items to the PDSD Filedrop at https://www.tucsonaz.gov/file-upload-pdsd. In the Project Description field, please include the Activity Number. 1) Comment Response Letter (lists changes made to the Plan and which reviewer comments you are responding to) 2) Complete Plan Set (all pages, full set) 3) Any other items requested by review staff After resubmittal, the plans will re-enter the standard 20-working-day review cycle. Thank you. Sharon Beasley, Permit Technician City of Tucson Planning and Development Services Attn: Permit Counter 201 N. Stone Avenue, First Floor Tucson, AZ 85701 |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/07/2019 | SBEASLE1 | OUT TO CUSTOMER | Completed |