| 07/18/2019 | SBEASLE1 | START | PLANS SUBMITTED | Completed | |
| 07/24/2019 | MGAYOSS1 | DESIGN PROFESSIONAL | REVIEW | Reqs Change | 7/24/19 - Applicant has not filed for IID/historic review. - María Gayosso |
| 08/01/2019 | MARTIN BROWN | COT NON-DSD | FIRE | Approved | |
| 08/05/2019 | SBEASLE1 | OTHER AGENCIES | TUCSON AIRPORT AUTHORITY | Approved | August 5, 2019 Sharon Beasley, Permit Technician City of Tucson Public Works Buildings - 201 North Stone Avenue Tucson, AZ. 85701 RE: DP19-0122 127 S. 5th Avenue, 8-story Residential Building / 2nd Submittal, Received July 18, 2019 Dear Ms. Beasley, Thank you for the opportunity to comment on DP19-0122, 127 S. 5th Avenue, 8-story Residential Building; 2nd Submittal, a development package application for an approximately 0.56 acre site, located northeast of the intersection of East 12th Street and South 5th Avenue. The property is zoned Commercial 3 (C-3), with the proposed development being an 8 story residential structure. The Tucson Airport Authority is satisfied with the 2nd submittal of the project and has no additional comments to provide. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811. Respectfully, Scott Robidoux, Senior Airport Planner |
| 08/12/2019 | PCAMARE1 | ZONING HC | REVIEW | Approved | |
| 08/12/2019 | PAUL CAMARENA | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Paul Camarena PDSD Zoning Review Section PROJECT: Multi-family - Residential Use Development Package (1st Review) 127 S. 5th Avenue DP19-0122 C-3 Zoning - IID-19-06; TRANSMITTAL DATE: August 9, 2019 DUE DATE: August 15, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is May 9, 2020. SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS) Section 2-06.3.0 FORMAT REQUIREMENTS 2-06.4.7.A - Zoning and Land Use Notes 2-06.4.7.A.6 - If a plan or plat is prepared in conjunction with other applications or overlays or the parcel being developed is subject to conditions of an application processed previously, additional information must be added to the plan. Such applications and overlays include, but are not limited to: annexations; rezonings; special exceptions; Board of Adjustment variances; Design Development Options; Technical Standard Modification Request; overlays (Airport Environs Zone, Environmental Resource Zone, Gateway Corridor Zone, Hillside Development Zone, Historic Preservation Zone, Major Streets and Routes, Rio Nuevo District, Scenic Corridor Zone, WASH); Modification of Development Regulations through the Downtown Area Infill Incentive District or Rio Nuevo District; Downtown Heritage Incentive Zone; or, Design Review Board. Provide the following information on the plan. 1. COMMENT: It is acknowledged that an IID application has been submitted for review. List the IID case number next to the title block of all plan sheets. Once the IID process has been completed include on sheet 2 the case number, date of approval and conditions of approval. This comment is still valid until IID condition are added to the plan. 2-06.4.8 - Existing Site Conditions 2-06.4.8.A - Provide site boundary/subdivision perimeter information, including bearing in degrees, minutes, and seconds, with basis for bearing noted, together with distances in feet, to hundredths of a foot, or other functional reference system. 3. COMMENT: The project is proposed over two existing parcels. Prior to approval of the DP the parcels will have to be combined. Contact the Pima County Assessor's Office for the Tax Parcel Combo process. This comment is still valid until the lot combination process is complete. 2-06.4.9.H.5.d - Show bicycle parking facilities fully dimensioned. For specifics, refer to Section 7.4.9, Bicycle Parking Design Criteria, of the UDC. Provide, as a note, calculations for short and long term bicycle spaces required and provided. 7. COMMENT: The number of bicycle parking spaces will be reviewed on the next submittal to verify compliance with the IID conditions. This comment is still valid until IID conditions are provided. Remove the word sidewalk on key note 35 on sheet 3. If you have any questions about this transmittal, Contact Paul Camarena at (520) 791-5550 or by email Paul.Camarena@tucsonaz.gov or contact Steve Shields at (520) 837-4956 or email Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 08/13/2019 | JENNIFER STEPHENS | PIMA COUNTY | ADDRESSING | Approved | The Addressing Review of DP19-0122 / 2nd submittal / 127 S. 5th Avenue is Approved by Pima County Addressing. Thank you, Thank you for your payment. Attached, please find your approved plans. Please let me know if you have any questions or if I may assist you further. Warm Regards, Robin Freiman Addressing Official Pima County Development Services Department 201 N Stone AV – 4th Floor Tucson, AZ 85701 (520) 724-7570 |
| 08/13/2019 | ZELIN CANCHOLA | COT NON-DSD | TRAFFIC | Approved | |
| 08/15/2019 | ANDREW CONNOR | LANDSCAPE | REVIEW | Reqs Change | 4.1 Identification and Descriptive Data The Development Package will contain the following: Any relevant information for reviews or modifications that affect the site. Provide IID approval information and any condition imposed. Landscape cannot approve plans until IID review is complete. Ensure that all Zoning and Engineering comments and concerns are addressed. |
| 08/20/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | DP19-0122 1) Previous Comment 1. Minimum width for a PAAL accessing 90 degree parking is 24'. The accessible parking spaces were shifted to the west. There is insufficient space behind the accessible parking space. Update as needed John Van Winkle, P.E. John.VanWinkle@tucsonaz.gov 520-837-5007 |
| 08/21/2019 | SBEASLE1 | COT NON-DSD | ENVIRONMENTAL SERVICES | Approved | The Environmental & General Services Department (EGSD) has reviewed the Development Package for the proposed apartment building to be located at 127 S 5th Avenue (DP19-0122). It is proposed to use a compactor unit to compact / store the refuse and recycling materials. The compactor will be located within an enclosure to be located along S Herbert Avenue on the east side of the property. The containers storing the compacted waste will be 2 cubic yards in size which will be rolled out to S Herbert Avenue for servicing three times per week. Information about the dimensions of the compactor were not provided in the Development Package. Therefore, EGSD could not check the dimensions of the enclosure to be sure there is adequate room for all of the compactor system components. Assuming the enclosure dimensions are sufficient to house the compactor unit, EGSD approves the use of a compactor unit for solid waste management at the 127 S 5th Avenue property. Please let me know if there are any questions concerning this review. Tom Ryan, P. E. City of Tucson - Environmental & General Services Department email: Thomas.Ryan@tucsonAZ.gov |
| 08/26/2019 | SBEASLE1 | ZONING-DECISION LETTER | REVIEW | Reqs Change | PLAN RETURNED FOR CORRECTIONS NOTICE - The reviews have been completed - A resubmittal is required Permit/Activity Number: DP19-0122 Description: SITE/GRADING/IID - 127 S. 5th Ave, 8-story residential building. Project Manager: John.VanWinkle@TucsonAz.gov, (520) 837-5007 The fee balance is $0 (zero). To view the review comments: www.tucsonaz.gov/PRO, enter Activity Number. (If information isn't shown yet, check back later as data flows to PRO periodically throughout the day.) Name your 3rd submittal documents accordingly, for example: 3_Plan_Set. Submit the following items to the PDSD Filedrop: https://www.tucsonaz.gov/file-upload-pdsd. In the Project Description field, please include the Activity Number. 1) Comment Response Letter (listing your response to reviewer's comments) 2) Plan Set (all pages, full set) 3) Any other items requested by review staff Thank you. Sharon Beasley, Permit Specialist City of Tucson Planning and Development Services Attn: Permit Counter/Payments 201 N. Stone Avenue, First Floor Tucson, AZ 85701 |
| 08/26/2019 | SBEASLE1 | COT NON-DSD | REAL ESTATE | Approved | Should there be any encroachment into CoT right of way the owner/developer will need to apply for the appropriate easement. Regards, Michael J. Hollar, SENIOR PROPERTY AGENT REAL ESTATE DIVISION DEPARTMENT OF TRANSPORTATION CITY OF TUCSON, 201 N. Stone Ave, 6th Floor Tucson, AZ 85701, Direct: 520-837-6784 Main: 520-791-4371 |