Review Date Reviewer's Name Type of Review Description Status Comments
04/24/2019 SBEASLE1 START PLANS SUBMITTED Completed
04/24/2019 SSHIELD1 ZONING HC REVIEW Approved
04/24/2019 SBEASLE1 OTHER AGENCIES PIMA ASSN OF GOVTS Passed A review is not required. This agency was notified for their information only.
04/24/2019 STEVE SHIELDS ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Steve Shields
Section Manager

PROJECT: JTED at the Bridges
Development Package (1st Review)
DP19-0093

TRANSMITTAL DATE: April 24, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is March 24, 2019.

CONTENT REQUIREMENTS

1. 2-06.4.3 - Provide the development package case number, DP19-0093, adjacent to the title block on all sheets.

2. 2-06.4.3 - Within the list of relevant case numbers you list C9-06-32 twice, please remove one of the references.

3. 2-06.4.3 - DP16-0094 & DP19-0054 needs to added the list of relevant case numbers and the table for Sub Area "A" needs to be updated to reflect all relevant information.

4. 2-06.4.3 - DP18-0257 needs to added the list of relevant case numbers and the table for Sub Area "F" needs to be updated to reflect all relevant information.

5. A copy of the Zoning Administrator approved charter school letter must be provided prior to building C of O.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
04/24/2019 SBEASLE1 UTILITIES SOUTHWEST GAS Passed A review is not required. This agency was notified for their information only.
04/24/2019 SBEASLE1 OTHER AGENCIES U. S. POST OFFICE Passed A review is not required. This agency was notified for their information only.
04/25/2019 MARTIN BROWN COT NON-DSD FIRE Reqs Change 1) Indicate on plans location of "No Parking-Fire Lane" signs for north fire access lane.
2) Please review table D103.4 of the 2018 International Fire Code (appendix D) for dead end roads exceeding 750'. Roads must be 26' wide AND approved by the fire code administrator.
3) It doesn't look like we can turn a fire truck around anywhere. Please review figure D103.1 of appendix D and recreate an approved turnaround on the drawing,
04/25/2019 TOM MARTINEZ OTHER AGENCIES AZ DEPT TRANSPORTATION Reqs Change Regional Traffic Engineering is requesting any documentation submitted pertaining to any impacts on the local, and Interstate, transportation network for our review and records. Please submit an ADOT (Traffic Engineering Guidelines and Processes) TGP From 240 to determine the proper traffic document for review and acceptance, if none were part of this development set.

Tom Martinez <tmartinez@azdot.gov>
04/26/2019 JOHN VAN WINKLE ENGINEERING REVIEW Reqs Change DP19-0093

1) Per Stormwater Detention/Retention Manual section 3.4.2 provide a grade control marker for the proposed detention/retention basin. On the plans please also provide the coordinates of the grade control marker so that it can be easily located in the future
2) Is there sufficient erosion protection along the slopes of the proposed basin above the drainage openings? Clarify and provide erosion protection as needed
3) Show how the proposed plan is in compliance with City of Tucson (COT) Unified Development Code (UDC) section 7.6.6.C. Particularly the grading of the vehicular use areas should be in such a manner that runoff is directed into landscaped areas. Curb cuts should be provided at optimal locations to allow runoff to enter landscaped areas. Available landscape area should be depressed up to 6" to maximize water harvesting. Provide spot grades in all depressed landscaped areas
4) Include the SWPPP site plan sheet found in the SWPPP manual in the develop plan. Update index/sheet numbering as needed
5) Provide a trash enclosure detail to meet TSM section 8. Note that clear area is measured inside bollards

John Van Winkle, P.E.
John.VanWinkle@tucsonaz.gov
520-837-5007
05/02/2019 SBEASLE1 OTHER AGENCIES TUCSON AIRPORT AUTHORITY Reqs Change May 2, 2019
Sharon Beasley
Permit Technician
City of Tucson
Public Works Buildings - 201 North Stone Avenue
Tucson, AZ. 85701
RE: DP19-0093 JTED at the Bridges, 1st Submittal, Received April 24, 2019
Dear Ms. Beasley,
Thank you for the opportunity to comment on DP19-0093, JTED at the Bridges, 1st Submittal, a development package application for an approximately 4.5 acre site, located southwest of the intersection of East Tucson Marketplace Boulevard and South Park Avenue. The property is zoned Planned Area Development (PAD-15), with the proposed development being a charter school use; elementary and secondary school.
This site is within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace.
The Tucson Airport Authority conditionally approves the subject request contingent upon the following condition of approval, as noted below. This condition shall be identified in the general notes of the revised development plan.

Condition of approval:
1. "According to the FAA Notice Criteria Tool, this project is located in proximity to a navigation facility and could impact navigation signal reception. The applicant shall file Form 7460 with the FAA at least 45 days before construction activities begin for the project. It is highly recommended that the applicant file earlier than 45 days to provide the applicant with sufficient time to respond to any concerns which are identified by the FAA. Any cranes used which are used must also be identified with Form 7460. Please file Form 7460 at https://oeaaa.faa.gov/oeaaa/external/portal.jsp"
Although this project does not propose a change in plan designation or zoning the Tucson Airport Authority highly recommends the City of Tucson consider requiring the applicant to add the following note into the general notes of the revised development plans. This project is located approximately 3 ½ miles north of Tucson International Airport and is within FAA traffic pattern airspace, an area which would be subject to aircraft overflight and noise due to being in close proximity to Tucson International Airport.
The proposed note would provide a means of assuring that future owners and tenants of the property are aware they are in proximity an airport and further assures the continued right of the City of Tucson, Tucson Airport Authority, and all persons lawfully utilizing the Tucson International Airport the right to utilize the airspace above or near the property. This would be accomplished through requiring the property owner to record the Avigation Easement. The Tucson Airport Authority believes the proposed note helps to support the City of Tucson Airport Environs Overlay Zone and supports Plan Tucson - Regional and Global Positioning policy 4 (RG-4).
1. "That prior to the City's approval of any construction permit for a permanent building, the property owner shall record the Avigation Easement which discloses the existence, and operational characteristics of the Tucson International Airport to future owners or tenants of the property and further conveys the right to the public to lawfully use the airspace above the property. The Avigation Easement shall be recorded in a manner with the Pima County recorder which shall document it as having title liability. The content of such documents shall be according to the form and instructions provided."
The current property owner or person authorized to sign on behalf of the current property owner shall complete, sign, and record the Avigation Easement. Please record the Avigation Easement with the Pima County Recorder's Office. Once the Avigation Easement is recorded please send a complete copy of the recorded easement document to Tucson Airport Authority by either email (send to srobidoux@flytucson.com) or to the mailing address provided below.
Scott Robidoux
Senior Airport Planner
Tucson Airport Authority
7250 South Tucson Boulevard
Suite 300
Tucson, AZ 85756
Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811.
Respectfully,
Scott Robidoux, Senior Airport Planner
05/03/2019 ANDREW CONNOR LANDSCAPE REVIEW Passed
05/03/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
05/13/2019 ZELIN CANCHOLA COT NON-DSD TRAFFIC Approved
05/14/2019 SBEASLE1 PIMA COUNTY ADDRESSING Reqs Change (The PDF attachment mentioned here can be viewed on PRO in the "Documents" section)

The Addressing Review of DP19-0093 / 1st submittal for review / JTED at the Bridges is being Returned for Corrections by Pima County Addressing.
The attached pdf contains Addressing’s comments.
Please let me know if you have any questions.
Thank you,
Robin Freiman, Addressing Official
Pima County Development Services Department
201 N Stone AV – 4th Floor Tucson, AZ 85701
(520) 724-7570
05/14/2019 SBEASLE1 COT NON-DSD PARKS & RECREATION Reqs Change Per PAD-15, the "Trail Connection Plan" (Figure 23, Page 73) shows a "30' trail easement" along the entire western boundary line of this parcel. In the "Clarification letter and Minor Amendment to PAD" letter dated April 2, 2011, in "Item 2" it is stated that a 30' easement along the western boundary of the property was granted on the Final Plat. I do not see any indication of this trail easement reflected on this Development Package.
Howard B. Dutt, RLA
Landscape Architect
Tucson Parks & Recreation
(520) 837-8040
Howard.Dutt@tucsonaz.gov
05/15/2019 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change PLAN RETURNED FOR CORRECTIONS NOTICE
The reviews have been completed and a resubmittal is required.
Activity Number: DP19-0093
Project Description: SITE/GRADING/SWPPP - JTED at the Bridges. Elementary and secondary (charter school).
To view review comments, visit PRO at www.tucsonaz.gov/PRO, then search by Activity Number. (If new comments aren't shown yet, check back later as data flows to PRO periodically throughout the day.) After all corrections are made, please name your 2nd submittal documents accordingly, for example: 2_Plan_Set.
Submit the following items to the PDSD Filedrop at https://www.tucsonaz.gov/file-upload-pdsd.
In the Project Description field, include the Activity Number.
1) Comment Response Letter (lists changes made to the Plan and which reviewer comments you are responding to)
2) Corrected Plan Set (all pages, full set)
3) Any other items requested by review staff
After resubmittal, the plans will re-enter the standard 20-working-day review cycle. The fee balance is $0 (zero).
The Project Manager can be reached via email or phone: Loren.Makus@TucsonAz.gov, (520) 837-4927
Thank you.
Sharon Beasley

City of Tucson
Planning and Development Services
Attn: Permit Counter
201 N. Stone Avenue, First Floor
Tucson, AZ 85701
05/15/2019 JOHN BEALL COT NON-DSD COMMUNITY PLANNING Approved
05/30/2019 LIZA CASTILLO UTILITIES TUCSON ELECTRIC POWER Approved (The TEP Facilities Map mentioned here can be viewed on PRO in the "Documents" section)

WR#6271806 May 30, 2019
City of Tucson
Attn: Sharon Beasley
Planning and Development Services
201 N. Stone Avenue, First Floor
Tucson, AZ 85701
Dear Ms. Beasley:
SUBJECT: JTED at the Bridges, DP19-0093
Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted April 24, 2019. It appears that there are no conflicts since there are no existing facilities within the boundaries of this proposed development.
Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer.
In order to apply for electric service, call the New Construction Department at (520) 918-8300. Submit a final set of plans including approved site, electrical load, paving off-site improvements and irrigation plans, if available include a CD with the AutoCAD version of the plans.
If easements are required, they will be secured by separate instrument. Your final plans should be sent to:
Tucson Electric Power Company
Attn: Mr. Richard Harrington
New Business Project Manager
P. O. Box 711 (DB101)
Tucson, AZ 85702
520-917-8726

Should you have any technical questions, please contact the area Designer, Martin Rodriguez, at (520) 917-8787.
Sincerely,
Linda Metzer, Office Support Assistant
Design/Build
cc: DSD_CDRC@tucsonaz.gov, City of Tucson (email)
M. Rodriguez, Tucson Electric Power

Final Status

Task End Date Reviewer's Name Type of Review Description
05/15/2019 SBEASLE1 OUT TO CUSTOMER Completed