Review Details: REVISION - - 3RD
Permit Number - DP19-0056
Review Name: REVISION - - 3RD
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/06/2021 | JPEELDA1 | FIRE | REVIEW | Approved | |
01/07/2021 | SBEASLE1 | DESIGN PROFESSIONAL | REVIEW | Approved | Date: January 5, 2021 From: Rick Gonzalez, Architect, City of Tucson On-Call Design Professional Re: Design Professional review comments for the modification 3 of DP19-0056, Hub 4. After review, based upon Main Gate District (MGD) Document and Ordinance 11394, Section C-19, of the required plans and documents submitted to PDSD, I recommend approval of this project revision 3. The project Civil engineer has made the following adjustments with respect to the Approved Design Package MGD-19-02, T19SA00139: Plan Set DP19-0056, Delta 3 Revisions 12/16/2020 COVER SHEET C1.0 -Clouded areas that changed on reference site plan SITE PLAN SHEET C3.0 -Overhead canopy was reduced in width and no longer sticks into right of way at NE corner. Aerial easement removed SITE PLAN SHEET C3.1 -An additional door was added along the store front near the NW corner. -A concrete ADA ramp (with handrail) was added north of the added door to accommodate the revised grading -Overhead canopy was reduced in width at NW corner. A revised aerial easement has been sent to city real estate. -Planter locations along Park Ave. were slightly adjusted to accommodate recommendations from TDOT landscape reviewer after DP approval. GRADING PLAN SHEET C4.1 -Grading was revised at NW corner to accommodate added door. PRIVATE UTILITY PLAN SHEET C5.1 -Relocation of existing street light electrical conduit was called out to avoid planters along Park Ave per recommendations from TDOT landscape reviewer after DP approval. -The relocated location of the FDC is shown on this sheet which was verified acceptable by TFD. -The gas meters were rotated to be along the building per direction from SWG -The fence along the west side of the generator enclosure was removed. CIVIL DETAILS PLAN SHEET C6.0 -Detail 3 was added for ADA ramp discussed above. -Detail 6 was modified to show a structural building element along east side of alley (onsite). 24’ travel way was maintained. HORIZONTAL CONTROL SHEET C7.1 -Horizontal control points were adjusted to match adjustments described above. LANDSCAPE PLAN SHEET L1.0 -slightly adjusted tree planter locations along Park to avoid fire service line and provide greater separation of tree canopies -Added vines in planters to climb trellis along Park and Tyndal IRRIGATION PLAN SHEET L2.0 -Adjusted irrigation to accommodate adjustments mention for L1.0 The Hub IV Development Package Revision 3 Submittal matches the last MGD-DRC approved package Revision (modification) presented in the 10/17/2020 approved revision 2, except for some minor revisions to canopy widths, an added door, and ADA modifications. Removal of screening on west side of the generator would be a problem if it occurred along a major street, but should be fine along the alley. Other changes such as responses to minor reviewer comments, adjustments to landscaping locations, can be considered minor changes, which I therefore recommend for approval as the Design Professional. No other deviations were found in this review. With Regards, Rick Gonzalez COT DP |
01/20/2021 | ANDREW CONNOR | LANDSCAPE | REVIEW | Approved | |
01/21/2021 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
02/11/2021 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
04/02/2021 | SAMUEL ROGERS | ZONING-DECISION LETTER | WRITE DECISION LETTER | Completed | |
12/31/2020 | SBEASLE1 | ZONING | REVIEW | Approved | 12/31/20 Approved by Steve Shields (see OK to submit). |