Permit Number: DP18-0304
Parcel: 11623063C

Address:
960 S FREEWAY

Review Status: Completed

Review Details: DEV PKG - OK TO SUBMIT

Permit Number - DP18-0304
Review Name: DEV PKG - OK TO SUBMIT
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/03/2020 SBEASLE1 START PLANS SUBMITTED Completed
06/03/2020 LOREN MAKUS ENGINEERING REVIEW Denied 1. Make sure all revisions are listed in the revision letter.
2. All items in the revision letter must be reflected in the plans.
06/04/2020 STEVE SHIELDS ZONING REVIEW Denied PDSD TRANSMITTAL

FROM: Steve Shields
Section Manager

PROJECT: The Tuxon
DP18-0304
Development Package

TRANSMITTAL DATE: June 4, 2020

The revision to the development package has been reviewed by the Zoning Review Section for minimal compliance with the Administrative Manual Section 2-06. It has been determined that the submitted plans and revision letter do not provide sufficient information to complete a plan review. The following items need to be addressed prior to re-submittal.

1. The revision letter talks about changes to "sheets, 1, 2, 3, 4 and 5" but does not address any changes to sheets 4 and 5.

2. The revision letter talks about "Removed a sidewalk ramp on the west side of the driveway connecting to 20th Street" but the ramp is still shown on the plan.

The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
06/04/2020 SBEASLE1 ZONING-DECISION LETTER WRITE DECISION LETTER Reqs Change REVISION PLAN DENIED FOR REVIEW NOTICE / Changes are required

Note: Please follow the steps below to resubmit your documents for review.

Permit/Activity Number: DP18-0304
Project Description: Revision #2 - SITE/GRADING - Tuxon Hotel, remodel.

To view the "Dev Pkg - Okay to Submit" (Start date 05/04/2020) comments by Reviewers online:
1. www.tucsonaz.gov/pro
2. Home page, left side - Activity Search
3. Enter the Activity Number (it's not case-sensitive)
4. Under "Permits" heading, click on blue tab (Permit/Activity Number)
5. In "Reviews" section, click on (blue) Review Details
(If complete information isn't shown yet, check back later after data transfers to PRO.)

After corrections are made, name your documents again as a first submittal of Revision # 2, for example: REV-2_Application.

Reminder:
When uploading on the Filedrop page, please check the box "Development Package or Land Division". This will include anything pertaining to the Development Package/Land Division Application form - new submittals, resubmittals, revisions, land splits, PDMR, TSMR, etc.
(Continue to select "Resubmittals/Revisions..." for Building permits).

Thank you.
Sharon Beasley, Permit Specialist

City of Tucson
Planning and Development Services
email: COTDSDPermits@TucsonAz.gov