Permit Number: DP18-0081
Parcel: 99999999A

Review Status: Completed

Review Details: TENTATIVE PLAT REVIEW

Permit Number - DP18-0081
Review Name: TENTATIVE PLAT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/05/2018 LPEREZ2 START PLANS SUBMITTED Completed
04/18/2018 ALEXANDRA HINES UTILITIES U. S. POST OFFICE Passed Agency notified for information only.
04/18/2018 AHINES2 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Passed Water acceptance for proposal under 6 lots.
04/18/2018 ALEXANDRA HINES UTILITIES PAG - PIMA ASSN OF GOVTS Passed Agency notified for information only.
04/18/2018 ALEXANDRA HINES UTILITIES SOUTHWEST GAS Passed Agency notified for information only.
04/26/2018 ZELIN CANCHOLA COT NON-DSD TRAFFIC Approved
05/01/2018 KELLY LEE PIMA COUNTY ADDRESSING Reqs Change MARKED UP PDF IS FOUND UNDER DOCUMENTS IN PRO.

DP18-0081 Houghton Town Center - Phase 2A is being returned for corrections by Pima County Addressing. The attached PDF contains Addressing’s comments. Please let me know if you have any questions.



Thank you



Nicholas Jordan

Addressing Specialist

Pima County Development Services Department

201 N Stone AV – 1st Floor

Tucson, AZ 85701

(520) 724-9623
05/03/2018 ACONNOR1 H/C SITE REVIEW Approved
05/03/2018 ANDREW CONNOR LANDSCAPE REVIEW Approved
05/03/2018 ANDREW CONNOR ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Andrew Connor, Planner

PROJECT:
Development Package (1st Review)
DP17-0014

TRANSMITTAL DATE: May 3, 2018

DUE DATE: May 3, 2018

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

The review comments include the actual standard first with the applicable Administrative Manual section number and the following paragraph is the actual comment related to the specific item that must be addressed. If you need to review the sections listed below click on the link or copy it in the address bar of your internet program. http://www.amlegal.com/nxt/gateway.dll/Arizona/tucson_az_udc/administrativemanual?f=templates$fn=default.htm$3.0$vid=amlegal:tucson_udc_az

This link will take you directly to the section used for the standards review. The UDC & TSM requirements are in the Unified Development Code and can be viewed at the same web link as above

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is , 2016.

SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)
Section


2-06.1.1 PURPOSE
This standard has been prepared for the purpose of informing applicants of the submittal and review requirements for development package documents to assure proper and adequate information is presented in a consistent manner, thereby providing the basis for an efficient and timely review. The development package documents are prepared in support of applications for building permits and related reviews.

The information that is requested establishes the basis upon which the project will be approved and could affect what is required of the property in the future, should there be a proposal for expansion or for a different use of the property.

This standard does not waive any applicable city regulations or codes.

2-06.1.2 APPICABILITY
This standard shall be used for all site plans and tentative plats submitted to PDSD for review.

CONTENT REQUIREMENTS

2-06.4.3 - The administrative street address and relevant case numbers (development package document, subdivision, rezoning, board of adjustment, DDO, MDR, DSMR, overlay, etc.) shall be provided adjacent to the title block on each sheet.

1. COMMENT: Provide the development package case number, DP17-0081, adjacent to the title block on each sheet.
Add the following note on cover sheet:
A separate development package must be prepared for each lot to the format and content requirements described in SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS).

The comments are minor the review can conducted over the counter

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package.
05/03/2018 MARTIN BROWN COT NON-DSD FIRE Approved
05/03/2018 ANDREW CONNOR NPPO REVIEW Approved
05/08/2018 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. The installation of a private sewer collection system requires a separate permit from the City of Tucson and will also require a review of the system design by the Pima County Department of Environmental Quality. Reference Title 18, R18-9-E302, 4.02 General Permit, Arizona Administrative Code.
2. The connection of a 6" building sewer to an 8" private sewer main will require the use of directional fittings: saddle-taps are not acceptable. Reference: Section 707, IPC 2012.
05/08/2018 GLENN HICKS COT NON-DSD PARKS & RECREATION Approved No existing or proposed Tucson Parks and Recreation facilities are affected by this development.





Howard B. Dutt, RLA

Landscape Architect
Tucson Parks & Recreation
(520) 837-8040

Howard.Dutt@tucsonaz.gov
05/09/2018 LOREN MAKUS ENGINEERING REVIEW Reqs Change 1. Revise references in the general notes to refer to the PAG standards rather than the PC/COT standards.
2. Check and correct the inspection request numbers in Grading Note 19.
3. Provide records of correspondence with El Paso Natural Gas for any construction within their easement.
4. Provide existing ground surface elevations throughout the site and for a distance of 50 feet outside the project area. (AM 2-06.4.8.E)
5. Show proposed ground surface elevations for all lots. (AM 2-06.4.9.N.4)
6. Show the floodplain information as described by AM 2-06.4.8.I.
7. Show completion of curb and sidewalk along Old Vail Road
05/16/2018 LIZA CASTILLO UTILITIES TUCSON ELECTRIC POWER Approved May 15, 2018



WR# 6229934

DSD_CDRC@tucsonaz.gov

Dear Kelly

SUBJECT: Houghton Town Center Phase 2A
10100 E Old Vail Rd
DP18-0081

Tucson Electric Power Company has reviewed and approved the development plan.

There are no apparent conflicts within the existing facilities, TEP facilities are shown on sheet 12. If relocation is required, all relocation cost is billable to the customer.

In order to apply for electric service, call the New Construction Department at (520) 918-8300. Submit a final set of plans including approved site, electrical load, paving off-site improvements and irrigation plans, if available include a CD with the AutoCAD version of the plans.

If easements are required, they will be secured by separate instrument. Your final plans should be sent to:
Tucson Electric Power Company
Attn: Rich Harrington
New Business Project Manager
P. O. Box 711 (DB-101)
Tucson, AZ 85702
520-917-8726

Should you have any technical questions, please call the area Designer, Juan Valenzuela @ 917-8714

Sincerely,
Beth Shelton
Elizabeth "Beth" Shelton
Admin Assistant, Design
05/16/2018 ALEXANDRA HINES ZONING-DECISION LETTER REVIEW Reqs Change This review has been completed and resubmittal is required. Please resubmit the following items:
1) Two rolled sets of the plans
2) All approved documents submitted previously
3) A disk containing all items submitted
4) All items requested by review staff
5) All items needed to approve these plans

Final Status

Task End Date Reviewer's Name Type of Review Description
06/08/2018 SVALENZ1 OUT TO CUSTOMER Completed