Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW
Permit Number - DP17-0123
Review Name: RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/20/2017 | ARUIZ1 | START | PLANS SUBMITTED | Completed | |
| 10/04/2017 | ALEXANDRA HINES | UTILITIES | TUCSON ELECTRIC POWER | Approved | Tucson Electric Power Co., (TEP) has reviewed and approves the attached revised Tentative Plat submitted to TEP by Perry Engineering on 10-3-17. The revision was to correct the easement label for Dkt 13016 Pg 1090 on Sheet 1 of the plat. If you have any questions, please contact me at 520-917-8744. Thank you, Mary Burke Right of Way Agent III Tucson Electric Power Co. Land Resources – RC 131 3950 E. Irvington Road Tucson, AZ 85714-2114 Office - 520-917-8744 Cell - 520-401-9895 mburke@tep.com |
| 10/11/2017 | DAVID RIVERA | ZONING | REVIEW | Approv-Cond | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: David Rivera for Steve Shields - Principal Planner PDSD Zoning Review Section PROJECT: Tentative Plat for Murphy's Lots 1 and 2 Development Package (2nd Review) DP17-0123 (Zoning is SR) TRANSMITTAL DATE: October 11, 2017 DUE DATE: October 18, 2017 COMMENTS: Conditional Approval This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is May 26, 2018. 1. Follow Up To Previous Comment 5: The building setback from the new west line to the existing dwelling was not added as requested. Add the building setback dimension on sheet 2, see redlines. 2-06.4.9.O - All applicable building setback lines, such as erosion hazard, floodplain detention/retention basins, and zoning, including sight visibility triangles, will be shown. PREVIOUS COMMENT 5: Label on sheet 2, the proposed building setbacks from the new property line to the chicken coop and the house. The minimum interior building setback in the SR zone is 25 feet. |
| 10/17/2017 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | 1. Revise note 24 to include both lots. Both lots are within the flood hazard area. 2. This correction will be reviewed over the counter if desired. |
| 10/18/2017 | KELLY LEE | ZONING-DECISION LETTER | REVIEW | Reqs Change | 1) Two rolled sets of the plans 2) All approved documents submitted previously 3) All items requested by review staff 4) All items needed to approve these plans |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/19/2017 | ARUIZ1 | OUT TO CUSTOMER | Completed |