Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: DEV PKG - RESUBMITTAL
Permit Number - DP16-0202
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/01/2017 | LBOJORQ1 | START | PLANS SUBMITTED | Completed | |
03/01/2017 | DAVID RIVERA | ZONING | REVIEW | Approv-Cond | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: David Rivera for Steve Shields - Principal Planner PDSD Zoning Review Section PROJECT: City Park Mixed Use - Downtown Development Development Package (3rd Review) DP16-0202 TRANSMITTAL DATE: March 1, 2017 DUE DATE: March 14, 2017 COMMENTS: Conditional Approval Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is November 14, 2017. 1. Zoning conditionally approves the Development Package; The revised Development Package must be reviewed, approved and signed off by the Design Professional to assure that all conditions of the IID approval have been incorporated into the DP or the appropriate documents are provided to the Design Professional. 2. If the Design Professional cannot approve the Development Package the conditional approval by Zoning is void. If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Conditional approval pending approval by the Design Professional. |
03/02/2017 | LIZA CASTILLO | UTILITIES | TUCSON ELECTRIC POWER | Approved | previous review |
03/02/2017 | PGEHLEN1 | COT NON-DSD | ENVIRONMENTAL SERVICES | Approved | previous review |
03/03/2017 | PAUL BAUGHMAN | ENGINEERING | REVIEW | Approv-Cond | The agreement of a fee to be paid to Park Wise for eliminating parking meters must be completed prior to issuance of a certificate of occupancy. A hold must be placed on the CofO for the building permit/TI prior to approval of this development package. |
03/06/2017 | MMENDIB1 | ZONING-DECISION LETTER | REVIEW | Needs Review | |
03/06/2017 | MMENDIB1 | LANDSCAPE | REVIEW | Needs Review | |
03/06/2017 | MMENDIB1 | DESIGN PROFESSIONAL | REVIEW | Needs Review |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/06/2017 | MMENDIB1 | OUT TO CUSTOMER | Completed |