Permit Number: DP16-0128
Parcel: 13348128E

Review Status: Completed

Review Details: SITE and/or GRADING

Permit Number - DP16-0128
Review Name: SITE and/or GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/08/2016 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
08/09/2016 MARTIN BROWN FIRE REVIEW Approved
08/15/2016 SSHIELD1 ADA REVIEW Passed
08/15/2016 STEVE SHIELDS ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Steve Shields
Principle Planner

PROJECT: Montesa Plaza Galaxy Theater
Development Package (1st Review)
DP16-0128

TRANSMITTAL DATE: August 15, 2016

DUE DATE: August 26, 2016

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is July 28, 2016.

CONTENT REQUIREMENTS

1. 2-06.3.9 - The plan drawing shall be oriented with north toward the top of the sheet. If it is not practical to orient north to the top of the sheet, the plan drawing shall be oriented with north to the left side of the sheet.

2. 2-06.4.3 - Provide the development package case number, DP16-0128, adjacent to the title block on each sheet.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

3. 2-06.4.7.A.4 - The proposed use listed under General Note 2 is not correct. The use should be listed as Entertainment, Excluding Large Dance Hall, subject to Use Specific Standards 4.9.4.C.3 and 4.9.13.O.

4. 2-06.4.7.A.6 - General Note 16 provide the UDC Article 5.3 for the Scenic Corridor Zone (SCZ).

2-06.4.7.A.8 - For development package documents provide:

5. 2-06.4.7.A.8.b - Remove General Note 9 as site coverage is not applicable.

2-06.4.8 - Existing Site Conditions
The following information shall be provided on the plan/plat drawing to indicate the existing conditions on site and within 50 feet of the site. On sites bounded by a street with a width of 50 feet or greater, the existing conditions across the street will be provided.

6. 2-06.4.8.A - Provide site boundary perimeter information, including bearing in degrees, minutes, and seconds.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

7. 2-06.4.9.F - Provide the zoning for the parcels to the south of this site and for the parcels north of Broadway and east of Houghton.

8. 2-06.4.9.H.5.a - Under the "PARKING CALCUALTIONS" revise "RECREATIONAL USE" to entertainment.

Once the above comments are addressed Zoning will provide an over-the-counter review. Call or email to schedule this appointment.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
08/15/2016 SSHIELD1 H/C SITE REVIEW Approved
08/24/2016 JOE LINVILLE LANDSCAPE REVIEW Approved
08/25/2016 JOE LINVILLE NPPO REVIEW Approved
08/26/2016 LOREN MAKUS ENGINEERING REVIEW Approved