Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: DP14-0226
Parcel: 99999999A

Address:
6105 E PIMA ST

Review Status: Completed

Review Details: SITE and/or GRADING

Permit Number - DP14-0226
Review Name: SITE and/or GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/02/2015 ANDREW CONNOR NPPO REVIEW Approved
01/05/2015 JASON GREEN ENGINEERING REVIEW Reqs Change DATE: January 5, 2015
DUE DATE: January 9, 2015
SUBJECT: Alamo Crossing Private Paving Development Plan Package- Engineering Review
TO: Oasis Tucson, Attn: Zach Hinman
LOCATION: 6105 E Pima St; T14S R14E Sec01
REVIEWERS: Jason Green, CFM
ACTIVITY: DP14-0226

SUMMARY: Engineering Division of Planning & Development Services Department has received and reviewed the proposed Development Plan Package. Engineering Division does not recommend approval of the Development Plan Package at this time. This review falls under the Unified Development Code (UDC), Administration Manual (AM) and Technical Standards Manual (TSM). Refer to the following link for further clarification:
http://www.amlegal.com/nxt/gateway.dll/Arizona/tucson_az_udc/administrativemanual?f=templates$fn=default.htm$3.0$vid=amlegal:tucson_udc_az

The following items need to be addressed:

SITE PLAN:

1) AM Sec.2-06.4.3: The relevant Development Plan Package case number (DP14-0226) may be added to the lower right hand corner of the plan on all sheets.

2) AM Sec.2-06.4.9.M: Verify that the private paving and public sewer plan matches the last approved development plan package (Tentative Plat) and under review Grading Plan Package in design, locations, dimensions and construction details for the project. All 3 plan sets should match for verification purposes. The private paving development plan package cannot be approved until approval of the grading development plan package.

GENERAL COMMENTS:

Please provide a revised Development Plan Package that addresses the comments provided above. For any questions or to schedule meetings call me at 837-4929.


Jason Green, CFM
Senior Engineer Associate
Engineering Division
Planning & Development Services Department
01/08/2015 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change A separate permit is required for the installation of a private sewer collection system handling over 3,000 gallons per day and will require a review of the system by the Pima County Department of Environmental Quality Reference Title 18, R18-9-E302, 4.02 General Permit, Arizona Administrative Code.
01/08/2015 KEN BROUILLETTE FIRE REVIEW Reqs Change Please indicate on site plan or drawings the location of existing and proposed fire hydrants for this project.
01/08/2015 RONALD BROWN H/C SITE REVIEW Reqs Change SHEET 3
1. At note 11 please be aware that detetectable warnings are required only at transportation platforms. They be installed at owner's option however the installation must be as per the 2009 ICC A117.1, Sections, 406.12, 13, 14 and 705.
SHEET 4
2. Detail H:
a. Comment 1 above is applicable for the curb ramps at the INTERIOR marked crossing.
b. At the most easterly sidewalk ramp insure a 5' x 5'
landing as required by ICC A117.1, Section 405.
c. Reference the accessible signage to detail O/6
3. Details G and I
a. Comment 1 above is applicable
b. Insure a 5' x 5' turn around landing at all 90 degree turn ramps as required by ICC A117.1, Section 405.
END OF REVIEW
12/10/2014 RBROWN1 ADA REVIEW Passed
12/29/2014 STEVE SHIELDS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Alamo Crossing
Development Package, Paving Plan Only (1st Review)
DP14-0226

TRANSMITTAL DATE: December 29, 2014

DUE DATE: January 09, 2015

1. The paving plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Zoning is not sure why this plan has been submitted as all required info should be on grading plan DP14-0197.

3. Zoning cannot approve the paving plan until approved by the Engineering review section.

4. Zoning will re-review the paving plan on the next submittal to insure compliance with the approved tentative plat. Additional comments may be forthcoming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
12/30/2014 ANDREW CONNOR LANDSCAPE REVIEW Reqs Change Ensure that all Zoning and Engineering comments and concerns are addressed prior to Landscape approval.

Final Status

Task End Date Reviewer's Name Type of Review Description
01/16/2015 KROBLES1 APPROVAL SHELF Completed
01/16/2015 KROBLES1 OUT TO CUSTOMER Completed