Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/08/2014 | AROMERO4 | START | PLANS SUBMITTED | Completed | |
10/08/2014 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
10/08/2014 | STEVE SHIELDS | ZONING | REVIEW | Approv-Cond | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Lead Planner PROJECT: Interstate Commerce Park Lots 8 -11 Development Package (2nd Review) DP14-0167 TRANSMITTAL DATE: October 8, 2014 DEVELOPMENT PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. The Zoning Review Section conditionally approves the development package for this project. 1. COMMENT: Zoning has reviewed the Covenants and Restrictions. Article 2 section 2.1 (b) states "However, if the City expressly permits a reduced number of parking spaces on a Parcel due to the inclusion of the Parcel in the Project, the reduced number of parking spaces satisfies the foregoing minimum parking requirement. This statement needs to be removed from the Covenants and Restrictions as the COT is not going to approve a reduction in parking unless the appropriate process, i.e. variance, has been approved. As the submitted development package does not show that each individual parcel meets the minimum required number of vehicle parking spaces for the use(s) on that parcel cross parking is required. The Covenants and Restrictions will need to be recorded prior to approval of the development package. If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov Sshield1 on DS1/planning/New Development Package/ DP14.0167 |
10/08/2014 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Approv-Cond | CCR issues will be dealt with at building permitting. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
01/14/2015 | CPIERCE1 | APPROVAL SHELF | Completed |
01/14/2015 | CPIERCE1 | OUT TO CUSTOMER | Completed |