Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/16/2017 | ARUIZ1 | START | PLANS SUBMITTED | Completed | |
05/16/2017 | ANDREW CONNOR | LANDSCAPE | REVIEW | Approv-Cond | Ensure that all Zoning and Design Professional comments and concerns of submitted revisions are addressed prior to landscape approval. |
05/16/2017 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Principal Planner PROJECT: AC Hotel Broadway Development Package (2nd Revision) DP14-0147 TRANSMITTAL DATE: May 16, 2017 DUE DATE: May 25, 2017 DEVELOPMENT PLAN COMMENTS: The Zoning Review Section conditionally approves the development package for this project subject to the following conditions: 1. 2-06.4.9.G - The revision letter talks about phasing and the plans show Phase 1 and Phase 2 but there is no development shown in Phase 2. Also if phasing is proposed provided all applicable calculations on the plan. If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov |
05/18/2017 | GARY WITTWER | COT NON-DSD | TDOT | Approved | Alex - I do not have any additional comments. Thanks, Gary |
05/19/2017 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | 1. Clarify the proposed 2nd phase. 2. Show and label the canopy over the south entrance. Include height over the sidewalk. |
05/19/2017 | ZELIN CANCHOLA | COT NON-DSD | TRAFFIC | Approved | |
06/05/2017 | CLAURIE1 | DESIGN PROFESSIONAL | REVIEW | Approved | Design Professional approval as of June 2nd: The changes to entry canopy and signage located on 5th Avenue and Broadway per drawings dated May 25, 2017complies with IID requirements. |
06/06/2017 | ALEXANDRA HINES | ZONING-DECISION LETTER | REVIEW | Reqs Change |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/12/2017 | ARUIZ1 | OUT TO CUSTOMER | Completed |