Permit Number: DP14-0119
Parcel: 117060620

Address:
238 N 4TH AV

Review Status: Completed

Review Details: DEV PKG - RESUBMITTAL

Permit Number - DP14-0119
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/10/2016 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
03/14/2016 LOREN MAKUS ENGINEERING REVIEW Reqs Change 1. Check the keynote used for the proposed new paved area along Hoff Avenue.
2. Clearly show drainage patterns including roof drainage and show how water harvesting will be integrated into site design in accordance with the IID conditions.

Floodplain:
1. The parcel will largely be removed from the 1-percent flood hazard area at the effective date of the proposed LOMR, June 13, 2016. If the applicant wishes to wait until the effective date for permit issuance, the following comments will not apply.

a. On the site plan show floodplain information including a notation the entire project is within a FEMA zone AE. (AM 2-06.4.8.I)
b. Provide water surface contours at the upstream and downstream ends of the project site. (AM 2-06.4.8.I)
c. Provide finish floor elevations for each structure on the site. The FFE for each structure must be at the regulatory flood elevation, one foot above the base flood elevation.
03/15/2016 FDILLON1 DESIGN PROFESSIONAL REVIEW Approved The Conditions listed in the IID approval have been met and the Development Package is approved.
04/04/2016 SSHIELD1 ZONING HC REVIEW Approved
04/04/2016 ANDREW CONNOR LANDSCAPE REVIEW Approv-Cond The plan has been reviewed by the Landscape / NPPO Section there are no issues regarding landscape, However, the submittal cannot be fully approve until all Zoning & Engineering, comments, concerns, and appropriate revisions have been addressed.
04/04/2016 STEVE SHIELDS ZONING REVIEW Reqs Change FROM: Steve Shields
Principal Planner

PROJECT: DP14-0119
238 N. 4th Avenue
Development Package - Food Service Use (Restaurant)

TRANSMITTAL DATE: April 4, 2016

DUE DATE: April 8, 2016

COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

This plan has been reviewed for compliance with the Development Package Standards listed in section 2-06 of the City of Tucson Administrative Manual. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC).

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is July 3, 2015.

1. 2-06.4.9.H.5.b - It does not appear that the vehicle parking space calculation is correct. Based on the square footage provided on the plan for all structures and outdoor seating areas the total number that should be used is 5,128 or 51 vehicle parking spaces required. As the 5,128 square footage differs from what was shown on the plan submitted for the IID review the plans may need to be reviewed by the IID. Contact Carolyn Laurie.

2. 2-06.4.9.H.5.d - It does not appear that the bicycle parking space calculation is correct. Based on the square footage provided on the plan for all structures and outdoor seating areas the total number that should be used is 5,128 or 3 short term spaces required. As the 5,128 square footage differs from what was shown on the plan submitted for the IID review the plans may need to be reviewed by the IID. Contact Carolyn Laurie.


If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
04/06/2016 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Comment not addressed; there is no mention of backflow protection on the drawings. [Initial comment: Reduced pressure backflow prevention assemblies are required to be installed directly after the water meter for buildings that have food service facilities. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, http://cms3.tucsonaz.gov/sites/default/files/water/docs/backflow-ordinance.pdf]
2. Comment not resolved; the drawings only indicate a 1" water service pipe being installed, not a different water meter as indicated in the response to the comments. [Initial comment: Tucson Water limits a 5/8" meter to a maximum demand of 15 GPM. Calculate the expected water demand for the proposed buildings and determine the size of the required water meter.]
04/08/2016 PGEHLEN1 ENV SVCS REVIEW Reqs Change Trish,




The City of Tucson - Environmental Services Department (ES) has completed our review of the Development Package for the Box Yard facility proposed at 238 N. 4th Avenue. The Development Package plans shall be revised to incorporate the following:



•IID Note No. 2 states that the enclosure is to be constructed to UDC standards. However, the double enclosure shown on Sheet 4 of 6 does not meet ES standards. However, ES will allow the non-compliant enclosure as the Box Yard site is within the IID and the waste containers will be rolled out of the enclosure to Hoff Avenue. Remove the 1.33 foot by 2 foot column in the center of the gates to allow easier access for rolling the containers out of the enclosure. The gates should be revised (enlarged) to cover the entire opening on the east side of the enclosure. If this revision results in the open gates extending into the alley, the enclosure can be moved west the necessary distance to not have this happen.
•The Development Package stated that the containers will be rolled out of the enclosure to Hoff Avenue for pick-up by the refuse truck. To provide for ease in container rolling and servicing, the grading should be revised to a grade of 0.5 percent in any direction.
•There is an overhead electric line located along the north edge of the enclosure and apron. Move the enclosure to the south so that the overhead line is not over the apron in accordance with TSM 8-01.5.3.B.
•State in General Note No. 20 that the recycling container will also be serviced once per week.

Please let me know if there are any questions concerning this review.



Thomas G. Ryan, P. E.

City of Tucson - Environmental Services Department
04/09/2016 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Reqs Change This review has been completed and resubmittal is required. Please resubmit the following items:

1) Two rolled sets of the plans
2) A disk containing all items submitted
3) All items requested by review staff
4) All items needed to approve these plans

Final Status

Task End Date Reviewer's Name Type of Review Description
04/13/2016 AHINES2 OUT TO CUSTOMER Completed