Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: DP14-0065
Parcel: 12112401A

Address:
5326 E PIMA ST

Review Status: Completed

Review Details: RESUB - SITE/GRADING ALL

Permit Number - DP14-0065
Review Name: RESUB - SITE/GRADING ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/06/2014 KEN BROUILLETTE FIRE REVIEW Approved
08/13/2014 STEVE SHIELDS ZONING REVIEW Approved
08/14/2014 JASON GREEN ENGINEERING REVIEW Reqs Change DATE: August 14, 2014
SUBJECT: Kadampa Meditation Center Development Plan Package- 2nd Engineering Review
TO: Metro TED; Attn: Lisa Bowers
LOCATION: 5326 E Pima St; T14S R14E Sec02
REVIEWERS: Jason Green, CFM
ACTIVITY: DP14-0065

SUMMARY: Engineering Division of Planning & Development Services Department has received and reviewed the proposed Development Plan Package and Drainage Report (Cypress Civil Development, 07APR14 revised 01AUG14) and Geotechnical Evaluation (Speedie and Associates, 18APR14). Engineering Division does not recommend approval of the Development Plan Package at this time. This review falls under the Unified Development Code (UDC), Administration Manual (AM) and Technical Standards Manual (TSM). Refer to the following link for further clarification:
http://www.amlegal.com/nxt/gateway.dll/Arizona/tucson_az_udc/administrativemanual?f=templates$fn=default.htm$3.0$vid=amlegal:tucson_udc_az

The following items need to be addressed:

SITE PLAN:

1) Complied.
2) Restated: AM Sec.2-06.4.3: The relevant Development Plan Package case number (DP14-0065) may be added to the lower right hand corner of the plan on all sheets. Specifically Sheet 6.
3) Complied.
4) Complied.
5) Complied.
6) AM Sec.2-06.4.9.H.1: Provide a General Note on the Development Plan Package (DP14-0065) referencing the TSMR Case #, date of approval and any conditions (if applicable).
7) Complied.
8) Complied.
9) Complied.
10) Complied.
11) Complied.
12) Complied.
13) Complied.
14) Complied.
15) Complied.
16) Complied.
17) Complied.
18) Complied.
19) Complied.
20) Complied.
21) Complied.
22) Complied.
23) Complied.

DRAINAGE REPORT:

24) Complied.
25) Complied.

GENERAL COMMENTS:

Please provide a revised Development Plan Package that addresses the comments provided above. For expedite purposes the development plan package can be reviewed over the counter (PDSD Engineering Division comment only) for stamp approval once the item has been addressed. Please call to schedule an appointment when ready.

For any questions or to schedule meetings call me at 837-4929.



Jason Green, CFM
Senior Engineer Associate
Engineering Division
Planning & Development Services Department
08/22/2014 ANDREW CONNOR LANDSCAPE REVIEW Approved
08/26/2014 RONALD BROWN HC SITE REVIEW Approved
09/02/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed