Permit Review Detail
Review Status: Completed
Review Details: RESUB - SITE/GRADING ALL
Permit Number - DP14-0041
Review Name: RESUB - SITE/GRADING ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/10/2015 | PATRICIA GEHLEN | ZONING | REVIEW | Approv-Cond | Further review will be require prior to issuance of the grading permit. The landscape, grading, SWPPP, drainage reports will have to match conditionally approved site plan. The proposed lots will require a plat (adding lot lines to the approved development package was not disclosed in the revision letter from the EOR. |
02/10/2015 | PGEHLEN1 | ZONING-DECISION LETTER | WRITE DECISION LETTER | Approv-Cond | Permits may not be issued until the landscape, grading, swppp, drainage report and all other items have been addressed. |
02/10/2015 | PGEHLEN1 | COT NON-DSD | TRAFFIC | Approved | Approved by TDOT. Zelin Canchola TDOT Engineering Review >>> Patricia Gehlen 02/09/2015 3:01 PM >>> All: |
02/10/2015 | JASON GREEN | ENGINEERING | REVIEW | Approv-Cond | DATE: February 10, 2015 SUBJECT: West End Station Development Plan Package- Engineering Review TO: Patricia Gehlen; CDRC Manager LOCATION: 855 W Congress St; T14S R13E Sec14 REVIEWERS: Jason Green, CFM ACTIVITY: DP14-0041 SUMMARY: Engineering Division of Planning & Development Services Department has received and reviewed the proposed/revised Development Plan Package. Engineering Division recommends conditional approval of the Development Plan Package at this time. This review falls under the Unified Development Code (UDC), Administration Manual (AM) and Technical Standards Manual (TSM). Refer to the following link for further clarification: http://www.amlegal.com/nxt/gateway.dll/Arizona/tucson_az_udc/administrativemanual?f=templates$fn=default.htm$3.0$vid=amlegal:tucson_udc_az SITE PLAN: 1) Engineering conditionally approves the revised site plan. Final approval of the development plan package is based on submittal of a revised grading plan, SWPPP and Drainage Report. The site plan sheets were reviewed for site compliance only and were not reviewed for construction details or drainage layout. Prior to final approval or construction the applicant must submit a full set of plans and supplemental information for review and approval. 2) Verify if a new MDR or DRB review is required due to the changes in number of units, configuration, and elevations. GENERAL COMMENTS: For any questions or to schedule meetings call me at 837-4929. Jason Green, CFM Senior Engineer Associate Engineering Division Planning & Development Services Department |
02/10/2015 | FDILLON1 | DESIGN EXAMINER | REVIEW | Approv-Cond | 2-10-14 1. Cover letter references revisions to elevations. No elevations included in plans. 2. Revisions to number of units / configuration / elevations require a re-review by the DRB. This review may be scheduled by contacting Michael Taku at 837-4963 or Michael.Taku@tucsonaz.gov FD |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
02/10/2015 | PGEHLEN1 | APPROVAL SHELF | Completed |
02/10/2015 | PGEHLEN1 | OUT TO CUSTOMER | Completed |
02/10/2015 | PGEHLEN1 | REJECT SHELF | Completed |