| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/15/2015 | EGALLET1 | START | PLANS SUBMITTED | Completed | |
| 09/18/2015 | TOM MARTINEZ | OTHER AGENCIES | AZ DEPT TRANSPORTATION | Approved | Regional Traffic Engineering has no comment on this submittal and supports its acceptance. Thank you. |
| 09/22/2015 | ZELIN CANCHOLA | COT NON-DSD | TRAFFIC | Approved | |
| 09/23/2015 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 09/25/2015 | ANDREW CONNOR | LANDSCAPE | REVIEW | Approved | |
| 09/25/2015 | ANDREW CONNOR | NPPO | REVIEW | Approved | |
| 09/25/2015 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
| 09/28/2015 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
| 09/29/2015 | MICHAEL ST. PAUL | HC SITE | REVIEW | Approved | |
| 09/29/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
| 10/02/2015 | BVIESTE1 | ZONING-DECISION LETTER | REVIEW | Approved | |
| 10/02/2015 | LIZA CASTILLO | UTILITIES | TUCSON ELECTRIC POWER | Approved | See additional documents in PRO 4350 E. Irvington Road, Tucson, AZ 85714 Post Office Box 711, Tucson, AZ 85702 October 1, 2015 The WLB Group Attn: David W. Little, P.E. 4444 E Broadway Blvd Tucson, AZ 85711 Dear David: SUBJECT: QUIKTRIP 1463 DP14-0020 WR #298027 Tucson Electric Power Company has reviewed and approved the development plan submitted to our office. It appears that there are conflicts with poles and new development as well as the new deceleration lane in ADOT ROW. Conflicts have been determined previously and were billable to the customer. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. In order to apply for electric service, call the New Construction Department at (520) 918-8300. Submit a final set of plans including approved site, electrical load, paving off-site improvements and irrigation plans, if available include a CD with the AutoCAD version of the plans. If easements are required, they will be secured by separate instrument. Your final plans should be sent to: Tucson Electric Power Company Attn: Mr. Richard Harrington New Business Project Manager P. O. Box 711 (DB-101) Tucson, AZ 85702 520-917-8726 Should you have any technical questions, please call the area Designer, Jennifer Necas, at (520) 918-8295. Sincerely, Natalie R Nava Scheduling Coordinator Design/Build Enclosures CC: Jennifer Necas, Tucson Electric Power Company CC: DSD_CDRC@tucsonaz.gov, City of Tucson (email) |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/06/2015 | KROBLES1 | OUT TO CUSTOMER | Completed |